2010 WI 58
|
Supreme Court of |
|
|
|
|
Case No.: |
2008AP921 |
|
Complete Title: |
|
|
|
E-L Enterprises, Inc., Plaintiff-Respondent, v. Milwaukee Metropolitan Sewerage District, Defendant-Appellant-Petitioner. |
|
|
|
|
|
REVIEW OF A DECISION OF THE COURT OF APPEALS 2009 WI App 15 Reported at: 316 (Ct. App. 2009-Published) |
|
|
|
|
Opinion Filed: |
July 2, 2010 |
|
Submitted on Briefs: |
|
|
Oral Argument: |
October 21, 2009
|
|
|
|
|
Source of Appeal: |
|
|
|
Court: |
Circuit |
|
County: |
|
|
Judge: |
Richard J. Sankovitz
|
|
|
|
Justices: |
|
|
|
Concurred: |
BRADLEY, J., concurs (opinion filed). ABRAHAMSON, C.J., joins concurrence. |
|
Dissented: |
PROSSER, J., dissents (opinion filed). |
|
Not Participating: |
|
|
|
|
Attorneys: |
|
For the defendant-appellant-petitioner there were briefs
by G. Michael Halfenger, William J. Katt,
Jr., and Foley & Lardner LLP,
For the plaintiff-respondent there were briefs by Jerome R. Kerkman, Susan A. Cerbins, Joseph
R. Cincotta, and Kerkman & Dunn,
An amicus curiae brief was filed by Daniel M. Olson and the League of Wisconsin Municipalities, Madison, on behalf of the League of Wisconsin Municipalities.
2010
WI 58
notice
This opinion is subject to further editing and modification. The final version will appear in the bound volume of the official reports.
REVIEW of a decision of the Court of Appeals. Reversed.
¶1 ANNETTE KINGSLAND ZIEGLER, J. This is a review of a published decision of the court of appeals,[1] which affirmed the judgment entered on a jury verdict by Milwaukee County Circuit Court, Richard J. Sankovitz, Judge. The jury found that when constructing a sewer, the Milwaukee Metropolitan Sewerage District (the Sewerage District) unreasonably removed groundwater from the property of E-L Enterprises, Inc. (E-L), which caused E-L's building to settle and amounted to a taking of E-L's property without just compensation. The jury awarded E-L damages in the amount of $309,388.
¶2 The Sewerage District filed a motion for judgment notwithstanding
the verdict on the grounds that the damages
E-L suffered to its property were consequential damages resulting from
governmental action and therefore were not compensable under the takings clause
of the Wisconsin Constitution.
Alternatively, the Sewerage District moved for a new trial based on
insufficient evidence to support the verdict.
The circuit court denied the Sewerage District's motions and awarded E-L
its attorney fees and costs. The circuit
court then entered judgment in the amount of $624,375.48 on behalf of
E-L and against the Sewerage District.
¶3 The Sewerage District appealed, and the court of appeals affirmed. The Sewerage District petitioned this court for review, and we accepted. We now reverse the decision of the court of appeals.
¶4 This case presents the following issues: (1) whether the Sewerage District's conduct constituted a taking of E-L's property without just compensation in violation of Article I, Section 13 of the Wisconsin Constitution and the Fifth Amendment of the United States Constitution;[2] and (2) whether E-L has established an inverse condemnation claim under Wis. Stat. § 32.10 (2007-08),[3] entitling E-L to attorney fees and costs.[4]
¶5 As a preliminary matter, we need not decide today the panoply of
issues that relate to an alleged taking of groundwater. In this case, E-L introduced no proof as to
the value of the extracted groundwater.[5] Instead, E-L seeks damages for the cost to
repair its building and for the loss of use of its wood piles. The Sewerage District did not physically
occupy the property for which E-L seeks compensation, and no government-imposed
restriction deprived E-L of all, or substantially all, of the beneficial use of
its property. Accordingly, what remains
are mere consequential damages to property resulting from governmental action,
which are not compensable under constitutional takings law.[6] The damage to
E-L's building was caused by the alleged negligent construction of the sewer;
hence, E-L's claim sounds in tort and seeks damages for which the Sewerage
District is not liable under the doctrine of governmental immunity. For the same reasons, we further conclude
that E-L has failed to establish an inverse condemnation claim under Wis. Stat.
§ 32.10. E-L is therefore not entitled to attorney
fees and costs under Wis. Stat. ch. 32.
Accordingly, this court reverses the decision of the court of appeals.
I. FACTUAL BACKGROUND AND PROCEDURAL POSTURE
¶6 In the 1980s, the Sewerage District constructed the Deep Tunnel
System, a 19 mile long system of sewers across Milwaukee County "that
help[s] reduce water pollution by storing excess wastewater 140 to 330 feet
underground" until the wastewater can be treated at reclamation
facilities.[7] The Deep Tunnel included the 1987-88
construction of the Crosstown 7 sewer (the sewer), a "near-surface
collector sewer" that collects sewage overflow and diverts it away from
the
¶7 To construct the sewer, BCI/TCI dug a trench, installed sewer
pipes, and restored the surface. A
portion of the sewer was constructed in the Sewerage District's easement under
a private alley adjacent to the subject building owned by E-L on
¶8 However, in order for BCI/TCI to properly lay the sewer pipe and
pour concrete, the trench had to be dry.
Accordingly, BCI/TCI pumped groundwater from the trench for 17
days. When the sewer was completed in
1988, groundwater measurements showed that the level of groundwater near
E-L's building had been significantly reduced.
It took two years for the groundwater level to recover.
¶9 In 1998, about ten years after the sewer project was completed, E-L's owner, Joseph Loftus, noticed that cracks in the foundation of his building appeared to be worsening, so he started to monitor the building's settlement rate. In 2001, an engineer examined the building's wood piles and determined that the caps of 14 wood piles had rotted and were no longer able to support the building. Those particular wood piles were under the south wall of E-L's building, nearest to the 1987-88 sewer construction site. In September 2003, E-L notified the Sewerage District of the building damage, and in October, E-L repaired the building. To repair the building, the damaged portions of the wood piles were sawed off and replaced with concrete. The repairs cost a total of $309,388, which includes E-L's attorney fees incurred in litigation with a neighbor who owned the adjacent alley and refused E-L access to make the building repairs. It is undisputed that E-L continued to lease the building throughout this entire period.
¶10 On June 23, 2004, E-L filed suit against the Sewerage District and CNA Insurance Companies (CNA), the insurer for the now defunct BCI/TCI. E-L alleged causes of action against the Sewerage District for negligence, continuing nuisance, and inverse condemnation and alleged causes of action against CNA for negligence and continuing nuisance.[9] The circuit court dismissed E-L's negligence and nuisance claims against the Sewerage District on the basis of governmental immunity under Wis. Stat. § 893.80(4).[10] Accordingly, only E-L's inverse condemnation claim remained.[11]
¶11 As to the inverse condemnation claim, E-L's complaint alleged that
the Sewerage District's operation and maintenance of the Deep Tunnel System and
the pipes constructed as a part of the sewer "physically took portions of
the wood piles which rendered them unusable and damaged the
E-L alleged that the Sewerage District's acts constituted a taking:
[The Sewerage District's]
conduct constitutes a taking of E-L Enterprises' property for public use. Specifically, [the Sewerage District's]
conduct constitutes a physical invasion that deprived and continues to deprive
E-L Enterprises of all beneficial use of the wood piles in violation [of] the
Fifth Amendment of the United States Constitution and Article I, Section 13 of
the Wisconsin Constitution.
. . . .
[The Sewerage District] took E-L Enterprises' property without paying E-L Enterprises its just compensation.
In addition to damages, E-L's complaint demanded attorney fees and costs relating to E-L's claim for inverse condemnation.[12]
¶12 E-L's takings claim under Article I, Section 13 of the Wisconsin Constitution proceeded to a jury trial. The special verdict form asked the jury whether the Sewerage District's removal of groundwater from E-L's property was a taking. To assist the jury in answering that question, the circuit court instructed the jury that the law bars the government from taking property for public use without compensating the owner and that "[g]roundwater is considered property of the person who owns the land under which it flows."[13] If the jury found that the Sewerage District's removal of groundwater from E-L's property was a taking, the jury was required to answer whether the removal of groundwater from E-L's property caused E-L's building to settle. If the jury answered that question in the affirmative, the jury had to determine the sum of money that would "justly compensate E-L for the taking of the groundwater beneath the south end of [E-L's] building."
¶13 The jury found that the Sewerage District's removal of groundwater from E-L's property was unreasonable, constituted a taking, and caused E-L's building to settle. The jury awarded E-L $309,388 "for the taking of groundwater" beneath its building——an amount equal to the cost to repair E-L's building and the attorney fees E-L incurred litigating with the neighbor who owned the adjacent alley and refused E-L access to make the repairs.
¶14 In its November 7, 2007 order, the circuit court denied the Sewerage District's motion for judgment notwithstanding the verdict or, in the alternative, a new trial and granted E-L's request for attorney fees and costs under Wis. Stat. ch. 32.[14]
¶15 The Sewerage District appealed, and the court of appeals affirmed,
concluding that the jury verdict supported
E-L's inverse condemnation claim under Article I, Section 13 of the Wisconsin
Constitution and Wis. Stat. ch. 32. E-L Enters., Inc. v.
¶16 According
to the court of appeals, this case is "most analogous" to this
court's decision in Damkoehler v. City of Milwaukee, 124
¶17 In concluding that the Sewerage District's conduct constituted an
"occupation" under Wis. Stat. § 32.10,
id., ¶7, the court of appeals
explained that "[t]he law in
¶18 Finally, the court of appeals concluded that the circuit court did
not err in awarding attorney fees and costs to E-L because E-L prevailed on its
inverse condemnation claim under Wis. Stat. § 32.10.
¶19 We now reverse the decision of the court of appeals.
II. STANDARD OF REVIEW
¶20 Whether government conduct constitutes a taking of private property
without just compensation is a question of law that this court reviews
de novo. R.W. Docks & Slips
v. State, 2001 WI 73, ¶13,
244
C. Coakley Relocation Sys. v. City of Milwaukee, 2008 WI 68, ¶14, 310
III. ANALYSIS
A. Takings Claim
¶21 Article I, Section 13 of the Wisconsin Constitution provides:
"The property of no person shall be taken for public use without just
compensation therefor." Likewise,
the Takings Clause of the Fifth Amendment of the U.S. Constitution, made
applicable to the States through the Fourteenth Amendment, provides that
private property shall not "be taken for public use, without just
compensation." Lingle v. Chevron
U.S.A. Inc., 544
¶22 Under the Wisconsin Constitution, two types of governmental conduct
can constitute a taking: (1) "an actual physical occupation" of private
property or (2) a restriction that deprives an owner "of all, or
substantially all, of the beneficial use of his property." Howell Plaza, Inc. v. State Highway Comm'n,
66
¶23 In this case, E-L does not claim that the Sewerage District's conduct constituted a regulatory taking. Rather, E-L claims that the Sewerage District "physically took" E-L's property.[15] E-L's brief asserts that the Sewerage District "physically took E-L's groundwater and deprived E-L of the use of that groundwater, resulting in the diminished value of E-L's property." E-L argues that by pumping groundwater from the trench, thereby extracting the groundwater from beneath E-L's adjacent building, the Sewerage District physically occupied or directly appropriated E-L's groundwater for the construction of the sewer. The removal of the groundwater damaged the building's wood piles, causing the building to settle and reducing the value of E-L's property. Because the groundwater was appropriated in connection with the installation of the sewer, which was created for the public's use and benefit, E-L claims that it is entitled to just compensation under both the Wisconsin Constitution and the U.S. Constitution.
¶24 E-L's takings claim must fail. E-L's claim morphed from a complaint that the Sewerage District "physically took portions of the wood piles which rendered them unusable and damaged the E-L Building" into a special verdict form that asked the jury to determine the sum of money that would "justly compensate E-L for the taking of [the] groundwater." The groundwater was indeed that which was extracted by the Sewerage District, but E-L introduced no proof as to the value of the extracted groundwater. Therefore, whether E-L owns the extracted groundwater is inapposite in this case.[16] E-L instead seeks damages for the cost to repair its building and for the loss of use of its wood piles. However, the Sewerage District did not physically occupy the property for which E-L seeks compensation, and no government-imposed restriction deprived E-L of all, or substantially all, of the beneficial use of its property. What remains are mere consequential damages to property resulting from governmental action, which are not compensable under Article I, Section 13 of the Wisconsin Constitution or the Takings Clause of the Fifth Amendment.
1. Whether
E-L owns the extracted groundwater
is inapposite in this case.
¶25 To determine whether a taking occurred, E-L argues that "the first question that must be addressed is whether property owners have a property right in groundwater." As E-L correctly points out, there can be no takings claim if that which the Sewerage District allegedly took is not E-L's property. However, E-L introduced no proof as to the value of the extracted groundwater. Instead, E-L seeks damages that flow from the allegation that when the Sewerage District pumped groundwater from the trench, the groundwater level beneath E-L's building was lowered, causing the wood piles to dry out and the building to settle. E-L's opening and closing arguments at trial make clear that instead of seeking damages for the value of the extracted groundwater, E-L seeks damages for the cost to repair the wood piles and E-L's building.
¶26 In its opening argument, E-L claimed that the Sewerage District took E-L's groundwater but consistently spoke of damage to E-L's wood piles and building:
[The Sewerage District] knew
that its partial taking of the property, taking of groundwater would result in
a lower value of E-L's building. You
take the groundwater, the piles rot, your building sinks, your building is not
worth what it was.
. . . .
As a result of [the Sewerage
District] taking groundwater, E-L's property lost value, the entire
property. We believe the value of the
building lost the value equal to the amount of the repairs that had to be done.
If I'm going to sell a house and you think it's worth $400,000,
and I know the roof needs to be repaired for $30,000, somebody buying that is
going to say, no, it's not $400,000, it's worth 370.
They're going to take out the value. And that's what E-L contends is the amount
taken. The loss in the value of their
property. And the amount that we're
seeking on that is just the amount E-L paid out of pocket.
. . . .
Everything we show you at trial is for you to see why E-L should be compensated for the taking of the groundwater by [the Sewerage District]. And how much money will equal the value of the groundwater taken by [the Sewerage District] and the harm caused to E-L from the damage to its piles.
¶27 Similarly, in its closing argument, E-L reiterated to the jury that E-L was seeking damages for the cost to repair its building:
The next question [on the
special verdict form] asks what amount should E-L be paid for its just
compensation. And here's where we're
going on this.
. . . .
. . . The reduction in the fair market value was what were the repairs that had to be done on this place.
And the repairs that had to be
done are summarized in Exhibit 51[17]
for you. There's multiple exhibits that
have all the invoices, but if you look at Exhibit 51, you're going to find a
summary.
. . . .
. . . The number we're asking for
when you add up all the number [sic] for the 2003 work, the 2004 work, and the
attorney fees, we had to fight, you know, we had an easement that was a very
standard easement.[18]
We had an [sic] to get permission to go underneath and dig under
that building. . . .
. . . .
So, ladies and gentlemen, when you add to the 2,300 from Dahlman, the 2003 expenses, the 2004, and legal fees, the number I come to is 309,388, and that's what I'm going to ask that you find as compensation for the amount of the taking.
¶28 It is clear from E-L's opening and closing arguments that instead of seeking damages for the value of the extracted groundwater, E-L seeks damages for the cost to repair the wood piles and E-L's building.
¶29 Because E-L introduced no proof as to the value of the extracted
groundwater, the court of appeals' reliance on Dahlman is misplaced.[19] It
is true, as noted by the court of appeals,
E-L Enters., 316
2. Mere consequential damage to property resulting from governmental action is not a taking thereof.
¶30 Both the United States Supreme Court and this court have
consistently recognized that "government action outside the owner's
property that causes consequential damages within" does not constitute a
taking. Loretto v. Teleprompter Manhattan CATV Corp., 458 U.S. 419, 428 (1982); see also Howell
Plaza II, 92 Wis. 2d at 80; Howell Plaza
I, 66
¶31 In Wisconsin Power & Light, this court recognized that
under the Wisconsin Constitution and the U.S. Constitution, "mere
consequential damage to property resulting from government action is not a
taking thereof." 3
¶32 Like E-L's damaged building and wood piles in this case, the
damaged tower "was not taken for public use in the usual sense of those
words."
¶33 Similarly, in this case, we conclude that the damages E-L suffered
are mere consequential damages to property resulting from governmental action,
which are not compensable under Article I, Section 13 of the Wisconsin
Constitution or the Takings Clause of the Fifth Amendment. E-L seeks damages for the cost to repair its
building and the loss of use of the wood piles.
However, the Sewerage District did not physically occupy E-L's building
or wood piles. The Sewerage District did
not use the building or wood piles in connection with the sewer installation,
and the public obtained no benefit from the damaged building or wood
piles. Rather, the wood piles were
damaged as a result of the Sewerage District's alleged negligent construction
of the sewer. Accordingly, we have in
this case "only damage, without appropriation to the public
purpose."
E-L's tort claims against the Sewerage District on the grounds of governmental
immunity under Wis. Stat. § 893.80(4).[23]
¶34 The court of appeals relied upon our decision in Damkoehler
for authority that the Sewerage District's diversion of groundwater that
supported the structural integrity of E-L's building constituted a compensable taking, as opposed to mere
consequential damage to property for which there is no remedy. See E-L Enters., 316
[T]he court [in Alexander] expressly declare[d] that it [did] not wish 'to be understood as asserting the doctrine that there must be an actual taking or appropriation of the property itself in order to entitle the owner to compensation for damages done him. The city might so build a bridge, or open a street, or excavate a canal along or upon a lot, only appropriating a small amount of it, or perhaps none of the land itself, and yet entirely destroy the value of the property for all purposes.' The instant case, in its facts, comes within the exception so distinguished by the court, and cannot be held to be ruled by the decision of that case.
¶35 The
distinction between Damkoehler and this case is significant. In this case, E-L does not claim that by
diverting the groundwater beneath E-L's building and thereby reducing the
building's structural integrity, the Sewerage District deprived E-L of all, or
substantially all, of the beneficial use of its building. Nor can E-L so claim. The fact that E-L continued to lease
the building throughout this entire period is alone sufficient to show that the
value of E-L's building was not destroyed for all purposes. Therefore, this case does not fall under the Damkoehler
exception to the well-recognized rule that mere consequential damage to
property resulting from governmental action is not a taking thereof.
B. Inverse Condemnation Claim
¶36
If any property has been occupied by a person possessing the power of condemnation and if the person has not exercised the power, the owner, to institute condemnation proceedings, shall present a verified petition to the circuit judge of the county wherein the land is situated asking that such proceedings be commenced. . . . The court shall make a finding of whether the defendant is occupying property of the plaintiff without having the right to do so. If the court determines that the defendant is occupying such property of the plaintiff without having the right to do so, it shall treat the matter in accordance with the provisions of this subchapter . . . assuming the plaintiff is not questioning the right of the defendant to condemn the property so occupied.
(Emphasis added.) By its terms, § 32.10 "is designed solely to deal with the
traditional exercise of eminent domain by the government: the government has
occupied private property, plans to continue such occupation and the landowner
is merely requesting just payment for this land." Zinn, 112
¶37 To state a cause of action under Wis. Stat. § 32.10 in the absence of actual possession or
occupation, this court concluded in Howell Plaza I that the facts
alleged must "show that the property owner has been deprived of all, or
practically all, of the beneficial use of his property or of any part
thereof." 66
¶38 Still, when a property owner alleges a constitutional taking, the
remedy provided by Wis. Stat. § 32.10
is not necessary to enforce the right to just compensation. Zinn, 112
¶39 In this case, E-L has failed to establish an inverse condemnation claim under Wis. Stat. § 32.10. It is undisputed that the Sewerage District did not physically occupy the property for which E-L seeks compensation, its building or the wood piles, and no government-imposed restriction deprived E-L of all, or substantially all, of the beneficial use of its property.[24] Therefore, the remedy provided in § 32.10 is simply inapplicable.
¶40 Because E-L has failed to establish an inverse condemnation claim under Wis. Stat. § 32.10, E-L is not entitled to its attorney fees and costs under Wis. Stat. § 32.28(3).
IV. CONCLUSION
¶41 In summary, we need not decide today the panoply of issues that relate to an alleged taking of groundwater. In this case, E-L introduced no proof as to the value of the extracted groundwater. Instead, E-L seeks damages for the cost to repair its building and for the loss of use of its wood piles. The Sewerage District did not physically occupy the property for which E-L seeks compensation, and no government-imposed restriction deprived E-L of all, or substantially all, of the beneficial use of its property. Accordingly, what remains are mere consequential damages to property resulting from governmental action, which are not compensable under constitutional takings law. The damage to E-L's building was caused by the alleged negligent construction of the sewer; hence, E-L's claim sounds in tort and seeks damages for which the Sewerage District is not liable under the doctrine of governmental immunity. For the same reasons, we further conclude that E-L has failed to establish an inverse condemnation claim under Wis. Stat. § 32.10. E-L is therefore not entitled to attorney fees and costs under Wis. Stat. ch. 32. Accordingly, this court reverses the decision of the court of appeals.
By the Court.—The decision of the court of appeals is reversed.
¶42 ANN WALSH BRADLEY, J. (concurring). I agree with the majority that mere
consequential damage to property resulting from government action is not a
taking. Majority op., ¶24. I also agree with the majority that the
essence of this case sounds in tort.
¶43 Over three decades ago, this court established that a property owner's
remedy for unreasonable interference with its use of groundwater sounds in
tort. State v. Michels Pipeline
Constr., Inc., 63
A possessor of land or his grantee who withdraws ground water from the land and uses it for a beneficial purpose is not subject to liability for interference with the use of water by another, unless
(a) The withdrawal of water causes unreasonable harm through lowering the water table or reducing artesian pressure . . . .
Restatement (Second) Torts, Tentative Draft No. 17, April 26, 1971, § 858A.[25]
¶44 Under the circumstances presented here, the withdrawal of groundwater may have caused unreasonable harm to E-L. But the remedy for this wrong sounds not in takings, but in tort.[26]
¶45 Indeed, as this case was presented to the jury, E-L's "takings" claim strongly resembled a tort claim. E-L argued that the District should have foreseen the harm and could have taken measures to avoid it. Additionally, E-L sought as damages the amount of money that it lost in rent and the amount of money that it paid out of pocket to repair the building.[27]
¶46 Further, portions of the jury instructions and special verdict also resembled a tort inquiry. For instance, the jury was instructed to determine whether the District's use of groundwater was unreasonable:
The burden is on E-L to satisfy you by the greater weight of the credible evidence, to a reasonable certainty, that the District's use of E-L's groundwater was unreasonable. In determining whether the District's use of E-L's groundwater was unreasonable, you should consider the District's need for the groundwater, E-L's need for the groundwater, the cost to E-L, if any, of the District's use of the groundwater, the cost to the District, if any, of not using the groundwater or of replacing the groundwater and whether the District's purposes for using E-L's groundwater could have been achieved through other means.
The reasonableness or unreasonableness of the District's actions is not a takings question——it is a tort question.
¶47 The circuit court determined that the District is immune from tort liability. E-L's attempt to dress up its tort claim in takings clothes to circumvent the District's immunity is unavailing. Accordingly, I respectfully concur.
¶48 DAVID T. PROSSER, J. (dissenting). At
trial, a jury found that E‑L Enterprises, Inc. (E-L) suffered $309,388 in
damages caused by the Metropolitan Milwaukee Sewerage District (MMSD). The majority does not dispute the accuracy of
these findings. Rather, it concludes
that E-L may not collect the damages awarded because they are
"consequential damages" that are not available to an injured party
under
¶49 Put in context, this ruling not only overturns a reasonable jury verdict but also deprives E-L of any meaningful remedy for its injury. This case, then, is important beyond the specific issues decided. It exposes the chasm between government wrongdoing and citizen redress. For the reasons stated below, I respectfully dissent.
I
¶50 In the 1980s, MMSD undertook construction of deep tunnels to hold sewage until it can be treated, thereby reducing water pollution. As part of this project, MMSD constructed the Cross Town 7 Collector System (CT-7) tunnel, which was located next to E-L's property. Before construction, MMSD detected the presence of groundwater in the vicinity. To construct the tunnel, project managers deemed it necessary to remove groundwater from the trench that would house the tunnel.
¶51 In the process of removing groundwater from the soil around the tunnel, MMSD also removed groundwater from E-L's property. The loss of groundwater caused 14 wood piles that were supporting E-L's building to rot. The jury determined that $309,388 was just compensation for E-L's costs to repair the piles.
¶52 On June 23, 2004, after repairing the piles, E-L filed suit against MMSD and CNA Insurance Companies, the insurers for the private contractors that participated in the construction of the deep tunnel project. E-L's complaint alleged five causes of action: (1) negligence against MMSD; (2) continuing nuisance against MMSD; (3) inverse condemnation;[28] (4) negligence against CNA; and (5) continuing nuisance against CNA. E-L settled with CNA prior to the trial of the case.
¶53 E-L did not enumerate five causes of action to increase its damages. E-L pled five causes of action because it was confronted with the challenge of grounding its claim for recovery in traditional legal theory. Because the facts of the case were unusual, the appropriate theory for the case was uncertain.
¶54 In its complaint, E-L presented its inverse condemnation claim as follows:
51. MMSD's operation and maintenance of the Deep Tunnel and the 48 inch sewer pipes which were constructed as a part of the Cross Town 7 Collector System physically took portions of the wood piles which rendered them unusable and damaged the E‑L Building.
52. MMSD's conduct constitutes a taking of E-L Enterprises' property for public use. Specifically, MMSD's conduct constitutes a physical invasion that deprived and continues to deprive E-L Enterprises of all beneficial use of the wood piles in violation of the Fifth Amendment of the United States Constitution and Article I, Section 13 of the Wisconsin Constitution.
(Emphasis added.)
¶55 By the time the case went to the jury, E-L had shifted the theory of its takings claim: MMSD did not "take" E-L's wood piles; MMSD "took" E-L's groundwater, thereby causing damage. The jury ultimately answered "yes" to the verdict question: "Was the District's removal of groundwater from E-L's property a taking?"
II
¶56 E-L also claimed negligence and nuisance. Both of these claims were dismissed by the circuit court. Initially, in March of 2006, the circuit court refused to dismiss these claims on grounds of governmental immunity. At the summary judgment stage, MMSD argued that its acts were "discretionary," not "ministerial," and therefore it was immune from liability. E-L, on the other hand, pointed to DNR-approved and –mandated groundwater depletion specifications, which prohibited MMSD and its contractors from lowering groundwater below existing levels.
¶57 Based on E-L's argument, the circuit court initially concluded that
"the act for which E-L seeks to hold MMSD liable——exceeding the groundwater depletion limitation——constitutes a transgression
in which MMSD had no discretion to engage." Relying on Lister v. Board of Regents of
the
¶58 In February of 2007, nearly one year after denying MMSD's motion for summary judgment and six months before the case proceeded to trial, the court revisited its earlier decision. In the course of deciding other motions, the court acknowledged a different provision in the same DNR-approved and –mandated specification. This provision required the contractor to control groundwater to perform work in the trenches in the dry, and to remove water when concrete is being placed and pipe is being laid. The circuit court concluded that "[d]iscretion is conferred [by the specification] because MMSD must exercise some judgment on how to obey both the duty to keep the excavation dry and safe as well as its duty not to draw the water down too low." Acknowledging that it made this ruling "relatively late in the game," the court dismissed both the negligence and nuisance claims. As a result, the parties proceeded to trial on the inverse condemnation claim alone.
¶59 Query: Isn't the natural remedy for the wrong in this case to be found in the law of negligence? Not if the court persists in unreasonably broad notions of governmental immunity and unreasonably narrow exceptions for tort recovery.[29] In any event, because the jury awarded E-L damages under a different legal theory from negligence, questions about governmental immunity were not raised in the petition for review, and the case before us involves only questions pertaining to the inverse condemnation claim.
III
¶60 In the absence of an adequate remedy in tort law, the only remedy
available to E-L comes from the Takings Clauses of the
¶61 In Luber v. Milwaukee County, 47
The importance of allowing recovery for incidental losses has increased significantly since condemnation powers were initially exercised in this country. During the early use of such power, land was usually undeveloped and takings seldom created incidental losses. Thus the former interpretation of the 'just compensation' provision of our constitution seldom resulted in the infliction of incidental losses. The rule allowing fair market value for only the physical property actually taken created no great hardship. In modern society, however, condemnation proceedings are necessitated by numerous needs of society and are initiated by numerous authorized bodies. Due to the fact people are often congregated in given areas and that we have reached a state wherein re-development is necessary, commercial and industrial property is often taken in condemnation proceedings. When such property is taken, incidental damages are very apt to occur and in some cases exceed the fair market value of the actual physical property taken.
¶62 In this case, although E-L seeks recovery for damages beyond the value of the groundwater, it does not go so far as to seek the kinds of consequential damages sought in Luber. Luber dealt with consequential damages beyond the reduction in "fair market value" of the property——the landowner sought lost rent. In this case, however, the jury awarded E-L the reduction in fair market value of its property. The circuit court instructed the jury:
If the government takes private property for a public use, the government must pay the owner the fair market value of the property that is taken. If only part of an owner's property is taken, and if taking part of the property reduces the value of the property that remains, the government must pay the difference between the fair market value of the property before the taking and the fair market value of the property after the taking.
¶63 Based on this instruction, the jury determined that E-L should be compensated in the amount of $309,388. Even though E-L presented this evidence in terms of the cost of repairing the piles, the cost of these repairs amounted to the reduction in value to E-L's property that resulted from MMSD's taking. The majority now reverses the decision of a properly instructed jury that determined the amount of compensation based on the evidence before it.
¶64 This point is further emphasized by E-L's initial claim that the "taking" was the taking of "portions of the wood piles" supporting the building. Whether MMSD "took" the wood piles or "took" the groundwater, the result was the same: MMSD took a portion of E-L's property, causing a reduction in fair market value to the remainder of that property.
¶65 Two early
¶66 In upholding the jury verdict in the present case, the court of
appeals correctly saw "no logical basis to distinguish between the removal
of soil providing lateral support and the diversion of groundwater performing
essentially the same function——that
is, supporting the structural integrity of a building like that owned by E‑L
Enterprises." E-L Enters., Inc.
v.
¶67 The majority distinguishes Damkoehler on grounds that the
landowner lost the entire value of the property. The court in Damkoehler, however, did
not limit its holding in that way. It
required that the city, in grading a street, "cause no unnecessary
damage to an adjoining landowner," and asserted that the city's actions
resulted in a taking "to the extent of such injury." Damkoehler, 124
¶68 Furthermore, the court in Dahlman held that a takings claim
could be maintained "where a substantial part" of the property fell
into the street. Dahlman, 131
¶69 The Damkoehler case has been cited in other jurisdictions,
including
The word "taken" in the constitutional
provision cited is not limited in its meaning and application to cases in which
there is an actual physical seizure and holding of property, but is broad
enough to include cases in which the access to abutting premises is obstructed
by the change of grade of a highway or there is such physical injury to
property as results in destruction or substantial impairment of its usefulness.
See 20 C.J. 697, and the
following cases therein cited: Nevins v. Peoria, 41 Ill. 502, 89 Am.
Dec. 392; Tinker v. Rockford, 36 Ill. App. 460; Hendershott v.
Ottumwa, 46 Iowa 658, 26 Am. Rep. 182; Offutt v. Montgomery County,
94 Md. 115, 50 A. 419; Vanderlip v. Grand Rapids, 73 Mich. 522, 41 N.W.
677, 3 L.R.A. 247, 16 Am. St. Rep. 597; Broadwell v. Kansas, 75 Mo. 213,
42 Am. Rep. 406; Mosier v. Oregon Nav. Co., 39 Or. 256, 64 P. 453, 87
Am. St. Rep. 652; Stearns v. Richmond, 88 Va. 992, 14 S.E. 847, 29 Am.
St. Rep. 758; Kincaid v. Seattle, 74 Wash. 617, 134 P. 504, 135 P. 820; Damkoehler
v. Milwaukee, 124 Wis. 144, 101 N.W. 706; Forbes v. Orange, 85 Conn.
255, 82 A. 559; Walters v. Baltimore [& Ohio R.]R. Co., 120
IV
¶70 At the end of the twentieth century, the United States Supreme
Court observed that the Takings Clause of the United States Constitution
prohibits government "from forcing some people alone to bear public
burdens which, in all fairness and justice, should be borne by the public as a
whole." Dolan v. City of Tigard,
512
We are not unmindful that other jurisdictions hold that damages resulting from landslides caused by excavations on highways in the course of improving them for public use are purely consequential, and not recoverable by the owner. We find the doctrine of liability under such circumstances more consonant with reason and justice . . . .
Damkoehler, 124
¶71 Because the majority expects E-L to suffer in legal silence, I respectfully dissent.
[1] E-L Enters., Inc. v.
[2] The issue of whether the Sewerage District's conduct constituted a taking under the U.S. Constitution was not invoked, argued, or appealed below. However, pursuant to our order, the parties briefed the issue before this court.
[3] All subsequent references to the Wisconsin Statutes are to the 2007-08 version unless otherwise indicated.
If any property has been occupied by a person possessing the power of condemnation and if the person has not exercised the power, the owner, to institute condemnation proceedings, shall present a verified petition to the circuit judge of the county wherein the land is situated asking that such proceedings be commenced. The petition shall describe the land, state the person against which the condemnation proceedings are instituted and the use to which it has been put or is designed to have been put by the person against which the proceedings are instituted. A copy of the petition shall be served upon the person who has occupied petitioner's land, or interest in land. The petition shall be filed in the office of the clerk of the circuit court and thereupon the matter shall be deemed an action at law and at issue, with petitioner as plaintiff and the occupying person as defendant. The court shall make a finding of whether the defendant is occupying property of the plaintiff without having the right to do so. If the court determines that the defendant is occupying such property of the plaintiff without having the right to do so, it shall treat the matter in accordance with the provisions of this subchapter assuming the plaintiff has received from the defendant a jurisdictional offer and has failed to accept the same and assuming the plaintiff is not questioning the right of the defendant to condemn the property so occupied.
[4] Pursuant to
[5] E-L sought damages for the cost to repair its building and the attorney fees and costs E-L incurred litigating with the neighbor who owned the adjacent alley and refused E-L access to make the repairs. At trial, E-L introduced proof of those damages. We are cognizant of the fact that the jury was asked to determine the sum of money that would "justly compensate E-L for the taking of the groundwater"; however, there was no proof introduced at trial as to the value of the extracted groundwater. See infra Part III.A.1.
[6] We have in this case
"only damage, without appropriation to the public purpose," and
therefore, E-L is unable to recover its damages on the theory of a
constitutional taking for public use. See
Wis. Power & Light Co. v.
[7] See the Milwaukee Metropolitan Sewerage District website http://v2.mmsd.com/deeptunnelhistory.aspx (providing the history of the Deep Tunnel System); http://v2.mmsd.com/deeptunnelhowitworks.aspx (explaining how the Deep Tunnel works).
[8] It is undisputed that neither BCI/TCI, the construction trench, nor the Sewerage District ever entered E-L's property.
[9] Before trial, CNA settled E-L's negligence and nuisance claims in a confidential agreement.
[10]
No suit may be brought against any volunteer fire company organized under ch. 213, political corporation, governmental subdivision or any agency thereof for the intentional torts of its officers, officials, agents or employees nor may any suit be brought against such corporation, subdivision or agency or volunteer fire company or against its officers, officials, agents or employees for acts done in the exercise of legislative, quasi-legislative, judicial or quasi-judicial functions.
E-L did not appeal the circuit court's dismissal of its negligence and nuisance claims against the Sewerage District; accordingly, that issue is not before this court.
[11] Within its cause of action for "inverse condemnation," E-L alleged both a constitutional takings claim and an inverse condemnation claim under Wis. Stat. § 32.10, although § 32.10 was not expressly referenced.
[12] In its order on July 19, 2007, before trial, the circuit court denied E-L's request for attorney fees and costs on the grounds that E-L did not have a claim for inverse condemnation under Wis. Stat. § 32.10. After the trial, the circuit court reconsidered its earlier order and decided that E-L was entitled to attorney fees and costs under ch. 32. Accordingly, E-L's entitlement to attorney fees and costs is an issue before this court on appeal.
[13] The Sewerage District objected to the circuit court's instruction that "[g]roundwater is considered property of the person who owns the land under which it flows":
[The Court]: . . . [The Sewerage District] deleted the sentence or propose to delete the sentence, "Groundwater is considered property of the person who owns the land under which it flows."
That statement is
true. It's not their exclusive
property. They don't have the right to
exclude others from using it, but they do have the right to use it, and Michels
[State v. Michels Pipeline Constr., Inc., 63
So as a matter of fact, it is E-L's property, not its property alone, but it is E-L's property. Otherwise if E-L doesn't have any property interest in here, game over. This case ends. If it has no property interest in it, they cannot make a claim for just compensation.
[Attorney James H. Petersen, counsel for the Sewerage District]: Your Honor, I guess that's precisely the point the District is getting at. Groundwater is a common good. If you have property, you have a right to use the groundwater that passes underneath your land, and even some of the groundwater that's under your neighbor's land, by virtue of your property ownership.
But it doesn't mean that that groundwater is yours to the exclusion of others.
[The Court]: I'm not saying that either, and my instructions don't say that either.
[Atty. Petersen]: These instructions allow that. They allow that to be argued.
[The Court]: First of all, it doesn't matter whether they allow that or not. The jury is not being asked to find that this was E-L's property exclusively.
In fact, the jury is being instructed to the opposite, that both the District and E-L and anybody else in that neighborhood had the right to use that property as long as they used it reasonably.
[14] See supra note 12.
[15] In its brief, E-L "asserts that the [Sewerage] District's taking was a physical, not regulatory, taking." Although E-L asserts that it is not claiming a regulatory taking, E-L's brief contradicts that by likening the Sewerage District's conduct to government regulatory action analyzed in Loretto v. Teleprompter Manhattan CATV Corp., 458 U.S. 419 (1982).
Loretto is an example of one of two categories
of regulatory action that is deemed a per se taking under the Fifth
Amendment. See Lingle v.
Chevron U.S.A. Inc., 544
At oral argument, E-L reiterated that its claim is based on the classic, not regulatory, category of taking: the Sewerage District's actual occupation or direct appropriation of E-L's property.
[16] While we recognize the significance of this issue, it is our position that its resolution is better reserved for a future case.
[17] E-L's repeated
reference to Exhibit 51 as a summary of its damages makes it readily apparent
that E-L seeks damages for the cost to repair its building, as opposed to the
value of the extracted groundwater.
Exhibit 51, a five-page document titled "Costs to Repair the
[18] The circuit court instructed
the jury that it was permitted to award E-L, as part of its just compensation,
the attorney fees that E-L incurred in litigation with the neighbor who owned
the adjacent alley and refused E-L access to make the building repairs. We conclude that the circuit court's
instruction was improper. As the circuit
court and the court of appeals correctly noted, under negligence law, when the
defendant's wrongful acts caused the plaintiff to expend legal fees with
another party, the expenditure is recoverable against the defendant. See Weinhagen v. Hayes, 179
[19] E-L also relies on Dahlman v. City of Milwaukee, 131
We
reject E-L's and the circuit court's characterization of Dahlman and Price. In Dahlman, this court concluded that
because a property owner, as against the city, is entitled to the lateral
support of the soil underlying the owner's property, there was a taking of the
soil when the city removed the lateral support in the course of street
grading. 131
[20] While
we take no position on the issue of whether a landowner owns the groundwater
beneath his property, we nevertheless determine that the circuit court erred by
instructing the jury that "[g]roundwater is considered property of the
person who owns the land under which it flows." Contrary to the circuit court's contention,
the jury instruction is not consistent with Michels Pipeline, 63
Our holding in Michels Pipeline recognized that while a landowner is permitted to withdraw groundwater for a beneficial purpose, he or she may be liable in tort for excessively withdrawing groundwater to the detriment of another's property. The circuit court dismissed E-L's negligence and nuisance claims against the Sewerage District on the basis of governmental immunity. As we previously noted, supra note 10, E-L did not appeal the dismissal of those tort claims.
Despite the dismissal of E-L's negligence and nuisance claims against the Sewerage District, the jury was nevertheless asked to determine if the Sewerage District's removal of groundwater from E-L's property was "unreasonable." As we have just explained, the withdrawal of groundwater in a manner that causes unreasonable harm to another's property may give rise to a tort claim. Because the circuit court dismissed the tort claims against the Sewerage District, the jury should not have been asked to evaluate the reasonableness of the groundwater removal.
Likewise, the jury was erroneously asked to determine
whether the Sewerage District's removal of groundwater from E-L's property was a
taking. Whether government conduct
constitutes a taking of private property without just compensation is a
question of law. R.W. Docks &
Slips v. State, 2001 WI 73, ¶13,
244
In this case, the special verdict form, which questioned the jury as to reasonableness and causation, was framed in terms of a negligence claim rather than a takings claim.
[21] For example, Article I, Section 15 of the Illinois Constitution provides: "Private property shall not be taken or damaged for public use without just compensation as provided by law." (Emphasis added.) For a list of other states with similar constitutional provisions, see 2A Julius L. Sackman, Nichols on Eminent Domain § 6.01[11], at 6-22 n.52 (3d ed. 2009).
[22] To reach its conclusion that the county's conduct did not constitute a taking, this court gave weight to the following facts:
[T]he tower had no utility, direct or indirect, to the highway project, that the county did not need or desire the tower or the land on which it rested and did not intend to acquire or affect either the tower or the land, that the public obtained no benefit from injuring it, that the county had no reason to anticipate that damage would result from its acts, and that the injury to the tower was purely accidental.
Here, the court of appeals erroneously distinguished
those facts from the facts in this case to conclude that the Sewerage
District's conduct "is on the 'taking' side of the line recognized by Wisconsin
Power & Light." E-L
Enters., 316
The court of appeals' reasoning is flawed in two
respects. First, the fact that this
court recognized in Wisconsin Power & Light that "the county
had no reason to anticipate that damage would result from its acts," 3
[23] Still, E-L is not without a remedy for the damage to its building caused by the alleged negligent construction of the sewer. Subject to the parties' confidential agreement, E-L has already been compensated an undisclosed amount by CNA, the insurer for the now defunct contractor.
[24] In concluding that the
Sewerage District's conduct constituted an "occupation" under Wis.
Stat. § 32.10, the
court of appeals explained that "[t]he law in
In Wikel,
the court of appeals reversed the circuit court's order dismissing the
plaintiff's petition for inverse condemnation under Wis. Stat. § 32.10. 247
As the court of appeals recognized, "'Land may be
taken for public purposes, within the meaning of the constitutional provision,
without actual occupancy or seizure by the taker.'"
Wikel is readily distinguishable from this
case. In Wikel, the plaintiff
claimed that the DOT's construction of the retaining wall rendered her property
"uninhabitable and unsaleable" and therefore constituted a
"total, permanent taking."
[25] This section was modified slightly before it was approved by the American Law Institute in 1979 as Restatement (Second) Torts § 858.
[26] In addition to filing tort and takings claims against the District, E-L also filed tort claims against the insurance company that insured BCI/TCI, the now-defunct subcontractor that constructed the tunnel. E-L and BCI/TCI settled the dispute for an undisclosed sum of money. Based on this record, it is unclear whether E-L has already been compensated in whole, or in part, for the cost of repairing its building.
[27] At closing arguments, E-L's
attorney explained: "And the cost to E-L in the District's use of that
groundwater . . . it's roughly $309,000 is what it's cost
E-L, plus loss of rent, what it's cost E-L because of the removal of the
groundwater outside the trench by the District."
When
there has been a partial taking, compensation is typically measured as either
(1) the fair market value of the portion of the property that was taken; or (2)
"severance damages," measured as the difference between the fair
market value of the property before the taking and the fair market value of the
remaining parcel after the taking.
Russell M. Ware, The Law of Damages in
[28] "Inverse
condemnation" describes "a cause of action against a governmental
defendant to recover the value of property which has been taken in fact by
the governmental defendant, even though no formal exercise of the power of
eminent domain has been attempted by the taking agency." U.S. v. Clarke, 445
[29] See Umansky v. ABC Ins.
Co., 2009 WI 82, ¶¶37-81,
319
[30] See U.S. Const.
amend. V ("[N]or shall private property be taken for public use without
just compensation"); Wis. Const. art. 1, § 13 ("The property of no person shall be taken
for public use without just compensation therefor."). The majority decides that E-L's damages are
not compensable under both the