COURT OF
APPEALS DECISION DATED AND
RELEASED June
27, 1996 |
NOTICE |
A party may file with the Supreme Court a petition to review an
adverse decision by the Court of Appeals.
See § 808.10 and Rule
809.62, Stats. |
This opinion is subject to further editing. If published, the official version will appear in the bound
volume of the Official Reports. |
No. 95-1899
STATE OF WISCONSIN IN
COURT OF APPEALS
DISTRICT IV
LEON
I. METZ, JOAN L. METZ
AND
METZ HONEY FARM, INC.,
A
WISCONSIN CORPORATION,
Plaintiffs-Appellants,
v.
PRISM
CORP., SOUTHWEST,
A
WISCONSIN CORPORATION,
Defendant-Respondent.
APPEAL
from an order of the circuit court for Grant County: GEORGE S.
CURRY, Judge. Affirmed.
Before
Eich, C.J., Dykman and Vergeront, JJ.
DYKMAN,
J. Leon I. and Joan L. Metz (Metz)
appeal from an order entered upon a jury verdict finding that Prism Corporation
had acted in good faith and had substantially performed a contract for the
construction of a honey processing facility, and that Prism was entitled to
recover $35,000 from Metz. Metz argues
that: (1) the trial court erred
when it denied Metz's motion for summary judgment because Prism did not
substantially perform the contract as a matter of law; (2) there is no
credible evidence to support the jury's verdict that Prism acted in good faith
and substantially performed; (3) repair costs and not diminished value
should be used to determine whether a party has substantially performed; and
(4) the form of the special jury verdict prevented the jury from
considering the issue of good faith.
We
conclude that: (1) the trial court
did not err in denying Metz's summary judgment motion because Prism presented
genuine issues of material fact as to whether it had substantially performed;
(2) credible evidence supports the jury's finding that Prism acted in good
faith and substantially performed; (3) diminished value, not repair costs,
are the proper measure of damages; and (4) the trial court did not erroneously
exercise its discretion when choosing the form of the jury verdict. Accordingly, we affirm.
BACKGROUND
In
April 1991, Metz hired Prism, a general contractor, to design and build a honey
processing facility. The contract
called for a five-inch reinforced concrete floor, pitched to drains where
possible, and for high efficiency boilers to be connected to two forced air
heaters owned by Metz. Prism or a
subcontractor was to provide the structural design of the foundation and
building. In return, Metz promised to
pay Prism $139,200. Construction began
on the facility in May 1991.
Prism
hired John and Greg Huza of Blackhawk Engineering, Ltd., who drafted site,
floor, concrete and plumbing plans. On
May 9, 1991, Greg Huza submitted a Plans Approval Application to the Department
of Industry, Labor and Human Relations (DILHR) for review of the footing and
foundation, building and structural components but not the heating, ventilating
and air conditioning (HVAC) plans.
Robert
Friesen, Prism's plumbing subcontractor, contacted Greg Huza to design the
heating plan. Friesen received a
"heat loss calculation" from Greg Huza in order to determine the
correct boiler size and bid on the project.
Metz met with Friesen, who agreed to install a radiant panel heating
system in the floor. The system would
have circuits of pipes embedded within the concrete floor. Hot water would be pumped by a boiler
through the pipes, heating the concrete floor and thus the interior of the
building. A boiler would be connected
to three heating zones. Two zones were
used for heating the building and the other would provide heat for honey
processing. On May 30, 1991, Prism
wrote to Metz, agreeing to provide heat and pipes in the floor for the system,
thereby raising the contract amount to $148,045.
The
floor heating system was installed and a flat concrete floor was poured in June
1991. Greg Huza prepared drawings
relating to the heating system after it was installed. He submitted a formal HVAC Plans Approval
Application to DILHR on August 20, 1991, almost two months after the heating
system was installed.
Metz
paid Prism $100,000 in July 1991, moved into the building, and began operations
in the beginning of August. Metz soon
discovered that the floors were not pitched and that puddles formed in various
parts of the facility. A Department of
Agriculture, Trade and Consumer Protection inspector determined that the floor
provided inadequate drainage. Metz
agreed to reconstruct the floor. The
department, nonetheless, recommended that Metz be issued a license.
Thereafter,
Metz met with Floyd Kunkel of Prism and Friesen to discuss the drainage
problem. It was decided that Prism
would pour another layer of concrete on the floor with pitches for the drains. No one consulted the Huzas or any other
engineer before pouring the additional concrete. As a result of adding another layer of concrete, the system's
heating efficiency was reduced.
Following
an inspection in April 1993, the department recommended that because the pipes
in the floor heating system were not approved by the manufacturer to carry hot
water or for use in concrete, Metz should either remove the pipes and replace
them with approved piping or install a different heating system. It ordered that if a different system was
installed, HVAC plans and specifications had to be approved by the department
prior to its installation. Metz
estimated that a new floor heating system and concrete floor would cost about
$75,000.
Metz
sued Prism and Friesen for breach of contract.
Prism counterclaimed against Metz for the balance due on the building
contract, arguing that it had substantially performed the contract. Prism also cross-claimed against Friesen for
contribution and later joined Blackhawk and Weber Concrete Services, the
concrete subcontractor. Metz moved for
summary judgment, arguing that Prism did not substantially perform the
contract. The trial court denied the
motion, concluding that genuine issues of material fact existed with respect to
whether Prism had substantially performed the contract. Metz settled with Friesen before the trial.
During
the trial, the trial court ruled, as a matter of law, that Prism and Friesen
failed to properly perform their duties under the terms of the contract. The jury was left to decide the amount of
damages owed to Metz to compensate him for the diminished value of the facility
due to Prism's and Friesen's failure to properly perform their duties and to
allocate responsibility between the two.
The jury was also asked whether Prism acted in good faith and
substantially performed its obligations under the contract and, if so, what sum
of money was Prism entitled to recover from Metz for work completed.
The
jury concluded that $30,000 would reasonably compensate Metz for Prism's
failure to properly perform the contract and that eighty percent (or $24,000)
was attributable to Prism and twenty percent (or $6,000) was attributable to
Friesen. The jury also found that Prism
had acted in good faith and substantially performed its obligations under the contract
and that Prism was entitled to recover $35,000 from Metz for work
performed.
Metz
moved to set aside the jury verdict as to whether Prism substantially performed
or for a new trial. The trial court
denied Metz's motion, set off the verdict amounts and granted judgment against
Metz in favor of Prism for $11,000.
Metz appeals.
I.
Metz
argues that the trial court erred in denying the motion for summary
judgment. He argues that Prism did not
substantially perform the contract as a matter of law because the contract
called for Prism to design and construct a honey processing facility and that
the facility, as built, is not operable for that purpose.
Summary
judgment is appropriate when all issues of material fact are undisputed. Brown v. LaChance, 165 Wis.2d
52, 60-61, 477 N.W.2d 296, 300 (Ct. App. 1991). The moving party has the burden of establishing the absence of a
disputed issue as to any material fact.
Id. at 61, 477 N.W.2d at 300. Where the moving party cannot meet this burden, summary judgment
is inappropriate. Id.
The
trial court found, as a matter of law, that Prism failed to properly perform
the contract. But a party's failure to
complete performance under a contract, or its defective performance, does not
prevent recovery if there is substantial performance of the contract. Tri-State Home Improvement Co. v.
Mansavage, 77 Wis.2d 648, 656, 253 N.W.2d 474, 477 (1977). The contractor must also have made a good faith
effort to perform. Id.
The
test for substantial performance is whether the performance meets the essential
purpose of the contract. Plante
v. Jacobs, 10 Wis.2d 567, 570, 103 N.W.2d 296, 298 (1960). Substantial performance should be granted in
cases of incompleteness only when such details are inconsiderable and not the
fault of the contractor. Tri-State,
77 Wis.2d at 656-57, 253 N.W.2d at 477.
Substantial performance does not require strict compliance with the
plans and specifications of a contract unless all details are of the
essence. DeSombre v. Bickel,
18 Wis.2d 390, 393, 118 N.W.2d 868, 870 (1963).
The
agreement between Metz and Prism provided that "Prism Corp., Southwest
proposes to construct an 8,000 square foot Honey Processing Facility: material, labor, freight, and tax are
included. The cost of 40,000 square
feet of land is also part of this proposal." As part of the general conditions, the contract provided: "Contractor shall provide the following
categories. Subcontractor shall provide
also relative to their work."
Those categories included:
Supervision, Architectural Design, Structural Design of Foundations,
Mechanical Design and Installation, Electrical Design and Installation.
On
summary judgment, Metz presented evidence pointing to Prism's improper
performance and its failure to substantially perform. Metz's expert, Dennis Volpe, averred that the facility "is
not much more than a minimally heated warehouse as opposed to a `honey
processing facility,' the use for which it was proposed." He also averred that Prism's heating
subcontractor, Blackhawk,
failed to properly calculate the heat loss which would
occur where a concrete heat panel system is used. This failure, along with the others documented, has left the owner
with substantially less than what was contemplated by the original
proposals.... The totality of the
defects, deficiencies, and areas of noncompliance with code are such that I can
conclude that there was not a reasonable effort made by the contractor, Prism
Corp., Southwest, the plumber, Robert Friesen, and the supervising and design
engineer of record, Gregory Huza of Blackhawk Engineering, in the planning and
building of the subject facility.
Volpe added that the piping used in the floor heating
system was not approved by the manufacturer for hot water or floor panel
heating systems, was not acceptable to the State and, therefore, was
unsuitable.
In
its defense on summary judgment, Prism deposed Volpe, who testified that while
he had recommended that Metz remove the entire concrete floor system and
install a new floor system which would cost about $75,000 and involve
reconstructing a substantial part of the facility, he also testified that the
concrete floor was suitable as a floor for all of Metz's needs. Floyd Kunkel, president of Prism, averred
that Prism was never furnished with any specifications outlining Metz's needs
but was given a rough sketch which consisted of a floor plan outlining the
proposed location of an office, warehouse, boiler room, loading dock and
processing room. He further averred
that at no time was he advised of the amount of honey Metz planned to process.[1]
Greg
Huza averred that the capacity of the boiler which was installed was more than
adequate for heating the building based upon Blackhawk's heat loss
calculations. He further averred that
he was never provided with any specifications detailing Metz's intentions
regarding honey production capacity and that if the hot water in the existing
boiler was used for both heating the building and processing the honey, the
capacity of the heating system could be directly affected but that other
measures short of tearing up the floor and installing a new heating system
could be adopted. Richard R. Geoffroy
averred that the pipes used in the floor heating system were suitable for that
system.
Based
upon this evidence, we conclude that Prism raised a factual dispute as to
whether Prism acted in good faith and substantially performed the
contract. In particular, there were
factual disputes concerning the type of building for which the parties
contracted, whether Prism should have and did consider the amount of honey to
be processed when designing and installing the heating and plumbing systems,
whether the heat loss calculation and boiler size had been properly measured
for the facility, whether it was necessary to tear up the entire floor or
whether other measures could repair the heating problem, and whether the pipes
in the floor were suitable for their intended use. Consequently, we conclude that the trial court properly denied
Metz's summary judgment motion.
II.
Metz
next argues that there was insufficient evidence to support the jury's verdict
that Prism acted in good faith and substantially performed. To reverse a jury verdict, we must find that
there is no credible evidence to support it.
Meurer v. ITT Gen. Controls, 90 Wis.2d 438, 450, 280
N.W.2d 156, 162 (1979). We view the
evidence in the light most favorable to the verdict and search for reliable
evidence that will sustain it. Id.
at 450-51, 280 N.W.2d at 162. We do not
search for evidence that would sustain a verdict the jury could have reached,
but did not. Id. at
450-51, 280 N.W.2d at 162-63. The
credibility of witnesses and the weight given to their testimony are left to
the jury, and where more than one reasonable inference may be drawn from the
evidence, we must accept the inference drawn by the jury. Id. at 450, 280 N.W.2d at 162.
To
show that a party has substantially performed, the contractor must have made a
good faith effort to perform, Tri-State, 77 Wis.2d at 656, 253
N.W.2d at 477, and the contractor's performance must meet the essential purpose
of the contract. Plante,
10 Wis.2d at 570, 103 N.W.2d at 298.
Good faith is defined as "honesty in fact in the conduct or
transaction concerned, that is, an honest intention to abstain from taking
unfair advantage of another ...." Wis J I Civil—3044.
The
evidence shows that a building was completed in which Metz is presently
operating a honey processing business.
Prism or its subcontractors provided designs and constructed the
facility. In particular, John Huza
drafted a site plan, floor plan, concrete plan and plumbing plan, and Greg Huza
designed the heating plan. Metz's
argument that Prism did not substantially perform turns on the extent to which
the heating system sufficiently satisfied the terms of the contract. He contends that the contract called for the
installation of a heating system that he could use to heat the facility and
process all of his honey. He asserts
that the system Prism and its subcontractors installed is inadequate and
defective.
But
the jury heard testimony from Friesen that while the pipes used in the heating
system were not recommended by the manufacturer for use in concrete, the State
had tested them and approved their use in Metz's building. Greg Huza testified that he was in the
building when it was nearly zero degrees outside and that he was comfortable
and warm inside. The trial testimony
also reveals that Metz never told Prism nor did the contract specify what size
boiler Metz planned to install. Friesen
testified that two vats would be hooked up to the system but that Metz never told
him how many pounds of honey would be processed or the amount of heat it would
require. He was only told that the
boiler Friesen would install would heat the building and the honey. After construction, Metz connected more vats
to the system than he originally told Prism.
Friesen, Volpe and Greg Huza testified that there were other ways to
improve the heating problem short of ripping out the entire floor system and
installing a new one. And Volpe
testified that the floor served its essential function as a floor. Greg Huza testified that when he met with
Friesen about the heating plan, he was not aware that the system would also be
used to process the honey. Kunkel testified
that it would cost about $2,000 to repair the building.
The
jury was presented with evidence that despite the defects and inadequacies, the
department had licensed Metz to produce honey and that Metz has been operating
the facility as a honey processing facility since 1991 and had increased his
output by about 500 percent. The jury
also heard evidence that Prism and its subcontractors attempted to meet Metz's
needs and offered to alter the contract to meet those needs. In other words, the deficiencies did not
defeat the essential purpose of the contract and there was credible evidence
upon which a jury could find that Prism had acted in good faith and
substantially performed.
Despite
this evidence, Metz nonetheless points to a statement in Tri-State
in which the court wrote that it could not hold, as a matter of law, that performing
four-fifths of the contract was substantial compliance. He argues that because the cost of repairing
the floor and installing a new floor heating system is more than one-fifth of
the entire project, we should also hold that Prism did not substantially
perform as a matter of law. We
disagree.
First,
we are generally hesitant to hold that a party has substantially performed a
contract as a matter of law. See
Wm. G. Tannhaeuser Co. v. Holiday
House, Inc., 1 Wis.2d 370, 373-76, 83 N.W.2d 880, 882-84 (1957). The supreme court has warned:
It is not easy to lay down rules for determining what
amounts to "substantial performance," sufficient to justify a
judgment for the contract price (subject to a counterclaim for injury, if
asserted) in any particular case. It
is always a question of fact, a matter of degree, a question that must be
determined relatively to all the other complex factors that exist in every
instance. The variation in these
factors is such that generalization is difficult and the use of cases as
precedents is difficult.
Id. at 373-74, 83 N.W.2d at 882-83 (quoting 3 Arthur Linton Corbin, Corbin On Contracts § 704).
Second,
in Tri-State, the jury found that the contractor did not
substantially perform the contract and the supreme court was only reviewing
whether there was credible evidence to support that verdict. The opposite is true here. The jury found that Prism substantially
performed and we need only find credible evidence to support that verdict.
Third,
the fact that the supreme court could not find as a matter of law that
four-fifths completion is not substantial performance does not require that we
reverse a jury verdict which concluded that Metz had substantially
performed. As the supreme court has
warned us: "No mathematical rule
relating to the percentage of the price, of cost of completion, or of
completeness can be laid down to determine substantial performance of a
building contract." Plante,
10 Wis.2d at 572, 103 N.W.2d at 298.
Where, as is here, there is credible evidence to support the jury's
verdict, we will affirm even when other evidence might reasonably lead to
another conclusion.
III.
The
trial court ruled that Prism failed to properly perform its contract. From this, Metz argues, Prism could not have
substantially performed its contract.
We disagree.
The
concepts of improper performance and substantial performance are not the
same. Just because a party has
improperly performed a contract does not mean that the party has not
substantially performed. The issue is
one of degree. The doctrine of
substantial performance is asserted when a party has not completely or
improperly performed. See Tri-State,
77 Wis.2d at 656, 253 N.W.2d at 477.
Metz
also cites Tri-State, 77 Wis.2d at 657, 253 N.W.2d at 477-78, as
supporting his position. But Tri-State
is not controlling. In Tri-State,
the trial court concluded that the contractor had not performed the contract
but did not find whether the contractor had substantially performed. Because of this, the court wrote,
"implicit in a finding that Tri-State did not perform the contract is a
finding that it did not substantially perform.
We presume the trial court was aware that if Tri-State had substantially
performed it was entitled to recover on the contract." But in this case, the trial court
specifically left the question of performance to the jury. Moreover, as we have concluded, just because
the trial court found that Prism did not properly perform does not mean that it
did not substantially perform.
Metz
also argues that because the trial court found that Friesen did not perform his
services in a workmanlike manner, Prism, as the general contractor, must be
held to a higher standard and is also liable.
Metz cites no legal authority in support of this proposition. We will not consider arguments unsupported
by reference to legal authority. State
v. Shaffer, 96 Wis.2d 531, 545-46, 292 N.W.2d 370, 378 (Ct. App.
1980). Moreover, we do not see how the
fact that Friesen did not perform in a workmanlike manner means that Prism did
not substantially perform or acted in bad faith.
IV.
Metz
next argues that repair costs, not the diminished value of the property, are
the proper measure of damages in this case and that the trial court erred when
it applied the diminished value rule.
We disagree.
It
is well settled that the measure of damages for defects and omissions in the
performance of building contracts is that the party is entitled to have what
the contract calls for or its equivalent.
DeSombre, 18 Wis.2d at 398, 118 N.W.2d at 872. But, if reconstruction and completion in
accordance with the contract involves unreasonable economic waste, then the
measure of damages is the difference between the value that the building would
have had if properly constructed and the value it has as constructed. W.G. Slugg Seed & Fertilizer, Inc.
v. Paulsen Lumber, Inc., 62 Wis.2d 220, 226, 214 N.W.2d 413, 416
(1974). In other words, when a
contractor has substantially but not completely performed, the owner is
entitled to the difference between the value of the building as it stands with
faulty and incomplete construction and the value of the building had it been
constructed in strict accordance with the plans and specifications. Plante, 10 Wis.2d at 572, 103
N.W.2d at 298-99. This is known as the
diminished value rule. The cost of
replacement or repair is not the measure of damages but is a factor considered
in arriving at the diminished value in some circumstances. Id.
Here,
the trial court heard evidence that ripping out the floor and heating system
and replacing it with a new one would cost about $97,000. The market value of the building was
assessed at between $107,900 and $145,300.
There was testimony that modifications could be made at much less
cost. Reconstruction and completion
would involve unreasonable economic waste.
The trial court therefore correctly applied the diminished value rule.
V.
Lastly,
Metz argues that the form of the special verdict prevented the jury from
considering good faith in two ways:
(1) by combining the issues of good faith and substantial
performance in one special jury verdict; and (2) by asking the jury what
amount of money would compensate Prism for its substantial performance without
qualifying the word "amount" with the phrase "if any." We disagree.
The
form of a special verdict rests in the discretion of the trial court and the
court's chosen form will not be rejected unless the inquiry, taken with the
applicable instruction, does not fairly present the material issues of fact to
the jury for determination. Topp
v. Continental Ins. Co., 83 Wis.2d 780, 785, 266 N.W.2d 397, 401
(1978).
In
one question the jury was asked, "Did Prism Corp. in good faith perform
and substantially perform its obligations under its contract with Leon and Joan
Metz?" The jury replied that it
did. This question required the jury to
find that Prism substantially performed and acted in good faith before
it could recover. The jury was
adequately instructed on the concepts of substantial performance and good
faith. The use of the conjunctive
indicated to the jury that it had to consider both issues separately and
independently and required it to answer both in the affirmative before it could
answer yes to the special verdict. This
verdict fairly presented the issues raised.
The trial court did not erroneously exercise its discretion by
submitting it.
We
do not consider whether the trial court erred by submitting a verdict that
asked how much money would compensate Prism for its substantial performance
without the phrase "if any" qualifying the word
"amount." Metz did not ask
that the phrase "if any" be added to the verdict question. Failure to request a jury instruction or
question prevents this court from considering whether the instruction or
question was erroneous. Section
805.13(3), Stats.; State v.
Schumacher, 144 Wis.2d 388, 409, 424 N.W.2d 672, 680 (1988).
By
the Court.—Order affirmed.
Not
recommended for publication in the official reports.
[1] Metz argues that under the parol evidence
rule, these discussions should not have been admitted because the contract was
plain on its face. Generally, when the
terms of a contract are unambiguous, the contract must be given its plain and
ordinary meaning and parol evidence is only admissible if the terms are
ambiguous. Energy Complexes, Inc.
v. Eau Claire County, 152 Wis.2d 453, 467-68, 449 N.W.2d 35, 40-41
(1989). Whether a contract provision is
ambiguous is a question of law. Moran
v. Shern, 60 Wis.2d 39, 46-47, 208 N.W.2d 348, 351 (1973). The contract provided that Prism and its
subcontractors would provide structural, mechanical and electrical designs for
the facility, but the contract is not clear that this included providing
designs and installations for just the building and not the honey processing as
well. Accordingly, we conclude that the
contract is ambiguous on this point and that these conversations were relevant
to show what Prism did and did not do and why.