COURT OF APPEALS DECISION DATED AND RELEASED July 2, 1996 |
NOTICE |
A party may file with the
Supreme Court a petition to review an adverse decision by the Court of
Appeals. See § 808.10 and
Rule 809.62, Stats. |
This opinion is subject to
further editing. If published, the
official version will appear in the bound volume of the Official Reports. |
No. 95-1772
STATE
OF WISCONSIN IN COURT OF
APPEALS
DISTRICT I
COMMERCIAL INDUSTRIAL
SERVICES
OF MILWAUKEE, INC.,
Plaintiff-Respondent,
v.
FREDERICK H.
GRIESHABER and
MILWAUKEE PRECISION
CASTING, INC.,
Defendants-Appellants.
APPEAL from a judgment
of the circuit court for Milwaukee County:
WILLIAM D. GARDNER, Judge. Affirmed.
Before Wedemeyer, P.J.,
Fine and Schudson, JJ.
PER
CURIAM. Frederick H. Grieshaber and Milwaukee Precision
Casting, Inc., appeal from a judgment of the circuit court enforcing a
materialman's lien in favor of Commercial Industrial Services of Milwaukee,
Inc.
Milwaukee Precision
argues that the following findings entered by the trial court are clearly
erroneous: (1) a gas leak at Milwaukee
Precision was not related to the work performed by Commercial; (2) the parties
had an oral contract for installation of additional gas piping by Commercial;
(3) the parties had an agreement to perform additional work on two boilers and
a heater owned by Milwaukee Precision; and (4) there was insufficient evidence
to support Grieshaber's counterclaim for slander of title. Grieshaber also argues that the trial court
misused its discretion by not allowing him to recover his costs and
disbursements incurred in defending the action brought by Commercial. We affirm.
Commercial is in the
business of repairing and maintaining heating, ventilating and air conditioning
systems. Milwaukee Precision
manufactures precision castings and molds.
Grieshaber is the president of Milwaukee Precision. After receiving a bid solicitation from
Milwaukee Precision to perform certain work, Commercial sent a proposal letter
to Milwaukee Precision outlining the amounts it would charge for the work
solicited. The proposal called for a
total payment of $6400. Of that amount,
$4200 was to be allocated to the installation of natural gas line piping. The balance of $2200 was payment for the
installation of a Cleaver Brooks boiler, which Milwaukee Precision would
supply. Grieshaber accepted the
proposal on behalf of Milwaukee Precision.
Sometime after the
installation of the piping, a gas leak developed. Commercial attempted to install the Cleaver Brooks boiler, but
discovered upon inspection of the boiler that it was non-operational. Commercial invoiced Milwaukee Precision for
the time spent inspecting the Cleaver Brooks boiler.
Rather than repair the
Cleaver Brooks boiler, Milwaukee Precision asked Commercial to inspect another
boiler, a York Shipley model. Upon
inspection, Commercial determined that this unit was also not suitable. Commercial billed Milwaukee Precision for
the amount of time it spent working on the York Shipley boiler. Milwaukee Precision also requested
Commercial to examine a Hastings heater.
Upon examination, Commercial discovered a large hole in the unit. Commercial billed Milwaukee Precision for
the amount of time it spent examining this heater.
In addition to
installing the gas piping provided for in the original contract, Commercial
installed an additional forty-two feet of gas piping. Commercial billed Milwaukee Precision for the installation of
this additional forty-two feet of gas piping.
Commercial invoiced
Milwaukee Precision for payment of all services rendered, including the
inspection of the two boilers and heater and for installing the additional
forty-two feet of gas piping. When
payment was not forthcoming, Commercial served a notice of intent to file a
claim for lien on Milwaukee Precision. After thirty days passed with no payment
of their invoices, Commercial filed a claim for lien against Milwaukee
Precision and Grieshaber pursuant to § 779.06, Stats. Thereafter, Grieshaber filed a counterclaim against
Commercial, alleging slander of title to his property.
The trial court entered
judgment against both Milwaukee Precision and Grieshaber. After a successful motion vacating judgment,
the trial court rendered a modification of judgment directing that judgment be
entered only against Milwaukee Precision and that Grieshaber be dismissed from
the case. Grieshaber, however, was
denied costs and disbursements.
Milwaukee Precision and Grieshaber's motion for reconsideration was subsequently
denied.
Standard of Review
We employ the clearly
erroneous standard when reviewing factual findings by a trial court. Section 805.17(2), Stats. This standard
is essentially the same as the “great weight and clear preponderance”
test. Noll v. Dimicelli's, Inc.,
115 Wis.2d 641, 643, 340 N.W.2d 575, 577 (Ct. App. 1983). Under the “great weight and clear
preponderance” test:
The evidence supporting the findings of the
trial court need not in itself constitute the great weight or clear preponderance
of the evidence; nor is reversal required if there is evidence to support a
contrary finding. Rather, to command a
reversal, such evidence in support of a contrary finding must itself constitute
the great weight and clear preponderance of the evidence.
Id., 115
Wis.2d at 643–644, 340 N.W.2d at 575, 577.
“When more than one
reasonable inference can be drawn from the credible evidence, the reviewing
court must accept the inference drawn by the trier of fact.” Cogswell v. Robert Shaw Controls, Inc.,
87 Wis.2d 243, 250, 274 N.W.2d 647, 650 (1979). We conclude, for the reasons set forth below, that the trial
court's findings of fact were not clearly erroneous.
1. Gas
Leak
The record submitted
before the trial court indicates that although both Grieshaber and the plant
manager of Milwaukee Precision testified that they smelled gas sometime after
Commercial completed its work, no evidence was presented as to the exact date
on which they began smelling the gas.
The only documentation regarding the repair of the gas leak was dated
almost six months after Commercial installed the gas piping. Further, Milwaukee Precision presented no
expert testimony indicating that the leaks were caused by Commercial's
installation of the gas piping. In
light of the evidence submitted, or lack thereof, the trial court's finding
that the gas leak was not related to the work performed by Commercial was not
clearly erroneous.
2. Installation
of Additional Piping
The record indicates
that the plant manager of Milwaukee Precision signed a field service report
authorizing the installation of an additional forty-two feet of gas
piping. Also, this employee testified
that he was in contact with Grieshaber regarding the report and that Grieshaber
did not object to the contents of the report. Further, the invoice sent to
Milwaukee Precision described the work completed as “additional.” Based on the foregoing, the trial court's
finding that an oral agreement existed between the parties for the installation
of the additional forty-two feet of gas piping was not clearly erroneous.
3. Boilers
and Heater
a. Cleaver
Brooks boiler. The record
indicates that after commencing work on the project, Commercial discovered that
the Cleaver Brooks boiler provided to them was not functioning. The record also indicates that a field
service report signed by Milwaukee Precision's plant manager authorized the
inspection of the boiler. The record
further indicates that the president of Commercial had numerous conversations
with Grieshaber regarding the results of the inspection and at no time during
these conversations did Grieshaber object to the testing. Therefore, the trial court's findings that
Milwaukee Precision authorized the inspection are not clearly erroneous.
b. York
Shipley boiler and Hastings heater. The trial court found that because the Cleaver Brooks boiler was
incompatible, Milwaukee Precision requested that Commercial inspect another
boiler, the York Shipley, as well as a heater for use in the project. This finding is supported by both the
testimony of Grieshaber and Milwaukee Precision's plant manager. This finding is also supported by the fact
that Milwaukee Precision's plant manager signed the field service report
confirming and authorizing the work on the York Shipley boiler and on the
heater. Because there is credible
evidence supporting the trial court's findings that the parties agreed to this
additional work, these findings are not clearly erroneous.
4. Grieshaber's
Costs and Disbursements
Grieshaber argues that
the trial court misused its discretion in denying him costs and
disbursements. Although the trial court
dismissed Commercial's claim as to Grieshaber personally, it declined to award
costs and disbursements to him, concluding that it would be inequitable to make
an award since he was so closely united-in-interest with Milwaukee
Precision. We agree. A trial court's decision to award or
disallow costs to a party is discretionary.
Chalk v. Trans Power Mfg., Inc., 153 Wis.2d 621, 634–637,
451 N.W.2d 770, 776–777 (Ct. App. 1989).
This court will affirm a trial court's discretionary decision if there
is any reasonable basis for it. Littmann
v. Littmann, 57 Wis.2d 238, 250, 203 N.W.2d 901, 907 (1973).
Section 814.03(2), Stats., states:
Where
there are several defendants who are not united in interest and who make
separate defenses by separate answers, if the plaintiff recovers against some
but not all of such defendants, the court may award costs to any defendant who
has judgment in the defendant's favor.
There
is sufficient credible evidence in the record to support the trial court's
determination that Grieshaber was united-in-interest with Milwaukee
Precision: (1) Grieshaber was president
of Milwaukee Precision; (2) Grieshaber was the sole owner of Milwaukee Precision;
(3) Grieshaber owned the building where Milwaukee Precision operated; and (4)
Grieshaber signed the initial contract entered into between the parties. The trial court did not misuse its
discretion in disallowing Grieshaber costs.
5. Slander of Title Counterclaim
Section 706.13(1), Stats., provides that:
In
addition to any criminal penalty or civil remedy provided by law, any person
who submits for filing, docketing or recording, any lien, claim of lien, lis
pendens, writ of attachment or any other instrument relating to the title in
real or personal property, knowing the contents or any part of the contents to
be false, sham or frivolous, is liable in tort to any person interested in the
property whose title is thereby impaired, for punitive damages of $1,000 plus
any actual damages caused thereby.
To
prove a violation of § 706.13(1), a party must prove that a “knowingly false,
sham or frivolous claim of lien or any other instrument relating to real or
personal property” has been filed, documented or recorded against that party
that impairs title. Kensington
Dev. Corp. v. Israel, 142 Wis.2d 894, 902–903, 419 N.W.2d 241, 244
(1988). A party must also show a
publication, which, in pertinent part, “plays a material or substantial part in
inducing others not to deal with [that party]” and “results in special
damages.” Id., 142 Wis.2d
at 902, 419 N.W.2d at 244. Grieshaber
failed to meet his burden. There is no
evidence in the record that shows that Commercial or any of its employees
knowingly filed a false claim. Further,
although Grieshaber argued that as a result of the filing of the lien he was
solicited by numerous bankruptcy attorneys and people were reluctant to do
business with him, Grieshaber produced no evidence that would indicate that he
or Milwaukee Precision sustained any compensable damages as a result of the
filing of the lien.
By the Court.—Judgment
affirmed.
This opinion will not be
published. See Rule 809.23(1)(b)5, Stats.