PUBLISHED OPINION
Case No.: 95-0458
Complete Title
of Case:
POWER SYSTEMS ANALYSIS, INC.,
Plaintiff-Appellant,
v.
CITY OF BLOOMER,
Defendant-Respondent.
Submitted on Briefs: September 14, 1995
COURT COURT
OF APPEALS OF WISCONSIN
Opinion Released: October 24, 1995
Opinion Filed: October
24, 1995
Source of APPEAL Appeal from a judgment
Full Name JUDGE COURT: Circuit
Lower Court. COUNTY: Chippewa
(If "Special", JUDGE: Roderick A. Cameron
so indicate)
JUDGES: Cane, P.J., LaRocque and Myse, JJ.
Concurred: Myse, J.
Dissented:
Appellant
ATTORNEYSOn
behalf of the plaintiff-appellant, the cause was submitted on the briefs of Carol
S. Dittmar and John D. Leary of Garvey, Anderson, Johnson, Gabler
& Geraci, S.C. of Eau Claire.
Respondent
ATTORNEYSOn
behalf of the defendant-respondent, the cause was submitted on the brief of William
G. Thiel of Weld, Riley, Prenn & Ricci, S.C. of Eau Claire.
COURT OF APPEALS DECISION DATED AND RELEASED OCTOBER 24, 1995 |
NOTICE |
A party may file with the
Supreme Court a petition to review an adverse decision by the Court of
Appeals. See § 808.10 and
Rule 809.62, Stats. |
This opinion is subject to
further editing. If published, the
official version will appear in the bound volume of the Official Reports. |
No. 95-0458
STATE
OF WISCONSIN IN COURT OF
APPEALS
POWER SYSTEMS
ANALYSIS, INC.,
Plaintiff-Appellant,
v.
CITY OF BLOOMER,
Defendant-Respondent.
APPEAL from a judgment
of the circuit court for Chippewa County:
RODERICK A. CAMERON, Judge. Affirmed.
Before Cane, P.J.,
LaRocque and Myse, JJ.
CANE, P.J. Power Systems Analysis, Inc. appeals a
judgment dismissing its complaint against the City of Bloomer. Power sought damages and injunctive relief
preventing the City from awarding a contract to Hooper Construction
Corporation, claiming that the City lacked the authority to accept Hooper's
late bid for a construction project.
Because we conclude that it is within the City's discretionary powers to
accept late bids for public construction contracts, we affirm the trial court's
dismissal of Power's complaint.
The relevant facts are
undisputed. In November 1994, the City
circulated a request for bids for the construction of an electric substation
and distribution facilities. The notice
stated that bids were due December 12, 1994, at 1 p.m. local time. Shortly after 1 p.m. on December 12, the
bids were opened. It was determined
that Power was the lowest bidder. Then,
at 2:30 p.m., the City received a late bid from Hooper that was $80,000 lower
than Power's bid.[1] The City subsequently awarded Hooper the
contract.
Power filed a complaint
against the City seeking declaratory and injunctive relief. The complaint alleged four causes of
action: (1) breach of contract; (2)
breach of statutory duty to award the contract to the lowest responsible
bidder; (3) no discretion to waive the untimeliness of the late bid; and
(4) abuse of discretion for awarding the contract to the late bidder. The trial court considered the parties'
briefs, affidavits and oral argument and ultimately ruled that: (1) the City
possessed the discretion to waive the untimeliness of the late bid; and (2) no
contract was formed when Power was initially informed it was the lowest
bidder. Therefore, the trial court
denied Power's request for injunctive relief and dismissed Power's entire
complaint with prejudice.
Power raises a single
issue on appeal: whether the City has
discretion to accept a late bid for work contracts after all timely bids have
been opened.[2] The issue presented in this appeal concerns
the construction of § 62.15, Stats.,
which is reviewed as a question of law without deference to the trial
court. State v. Pham, 137
Wis.2d 31, 33-34, 403 N.W.2d 35, 36 (1987).
Section 62.15, Stats., governs contracts for public
construction that exceed $10,000 and provides in relevant part:
(1) Contracts; how let. All public construction, the estimated cost
of which exceeds $10,000, shall be let by contract to the lowest responsible
bidder; all other public construction shall be let as the council may
direct....
....
(5) Rejection
of bids. The power to reject any
and all bids shall exist unless expressly waived. The board of public works may reject any and all bids, if, in
their opinion, any combination has been entered into to prevent free
competition. The council may, if it be
of the opinion that any of the bids are fraudulent, collusive, excessive or
against the best interests of the city, by resolution adopted by two-thirds of
its members, reject any or all of the bids received and order the work done by
the city directly under the supervision of the board of public works ....
Neither party disputes
that under § 62.15(1), Stats.,
certain contracts shall be let only to the lowest responsible bidder. Additionally, neither party disputes the
City's power under § 62.15(5), Stats.,
to reject any and all bids, unless the power is expressly waived. At issue is whether the City has the
discretion to open a late bid after the timely bids have been opened.
Power argues that when
the City was presented with the late bid, it had two choices under § 62.15(1)
and (5), Stats.: accept the lowest timely bidder (Power), or
reject all bidders and reopen the project for bidding. Power argues that because the City did
neither, the City's action was "clearly outside the statutory
directives" found in § 62.15(1).[3] Additionally, Power offers decisions from
numerous other jurisdictions in support of its position that late bids are not
capable of acceptance.[4]
Like Power, the City
argues that § 62.15, Stats., is
clear. However, the City disagrees with
what the statute clearly provides. The City
states, "[T]he legislature has simply not spoken to the issues of
establishing a bid opening time and the acceptability or unacceptability of
considering bids submitted thereafter."
Therefore, the City argues, because the legislature has failed to speak,
courts should be hesitant to engage in micro management of local, municipal
affairs.
The purpose of the rules
of statutory construction is to give effect to the legislative intent. Pham, 137 Wis.2d at 34, 403
N.W.2d at 36. When determining legislative
intent, this court first examines the language of the statute itself and will
resort to extrinsic aids only if the language is ambiguous. Id.; In re P.A.K.,
119 Wis.2d 871, 878, 350 N.W.2d 677, 681-82 (1984). If a statute is ambiguous, we look to its content, subject
matter, scope, history and the object to be accomplished to ascertain its
reasonable meaning. Boltz v.
Boltz, 133 Wis.2d 278, 284, 395 N.W.2d 605, 607 (Ct. App. 1986). A statute is ambiguous if reasonable persons
could disagree as to its meaning, and whether a statute is ambiguous is a
question of law. Id.; In
re D.S., 142 Wis.2d 129, 134, 416 N.W.2d 292, 294 (1987). Absent any ambiguity, this court gives the
language its ordinary meaning. State
ex. rel. Frederick v. McCaughtry, 173 Wis.2d 222, 225-26, 496 N.W.2d
177, 179 (Ct. App. 1992).
We begin with our
examination of the statute's language. Pham,
137 Wis.2d at 34, 403 N.W.2d at 36. We
agree with both parties that § 62.15(1), Stats.,
requires that contracts be awarded to the lowest responsible bidder and that
under § 62.15(5), Stats.,
cities are explicitly authorized to reject bids. Furthermore, we observe that the statute does not address the
specific details of the bidding process or a city's power to accept late bids. We agree with the City that this silence
signifies not ambiguity but a legislative decision to leave specific aspects of
the bidding process to the discretion of each city. Therefore, we conclude that while § 62.15 does not
explicitly authorize a city to accept a late bid, a city is not precluded from
doing so under the statute. Instead,
the decision is within the City's discretionary powers and is subject to
judicial review. See State
ex rel. Hron Bros. v. Port Washington, 265 Wis. 507, 509-10, 62 N.W.2d
1, 2 (1953).[5]
Our conclusion that the
City has discretion to accept late bids is consistent with our supreme court's
observation that statutes conferring the power to let contracts to the lowest
responsible bidder imply the exercise of discretion. Aqua-Tech, Inc. v. Como Lake Protect. &
Rehab. Dist., 71 Wis.2d 541, 549, 239 N.W.2d 25, 29 (1976).[6] Additionally, our conclusion follows our
supreme court's directive that statutory bidding provisions be read in light of
the reason for their enactment, lest they be applied where they were not
intended to operate and thus deny the authorities the ability to deal with
problems in a sensible, practical way. Waste
Management, Inc. v. Wisconsin Solid Waste Recycling Auth., 84 Wis.2d
462, 470, 267 N.W.2d 659, 663-64 (1978).
Statutory bidding
requirements are designed to prevent fraud, collusion, favoritism and
improvidence in the administration of public businesses, as well as to insure
that the public receives the best work or supplies at the most reasonable price
practicable. Aqua-Tech,
71 Wis.2d at 550, 239 N.W.2d at 30 (citing Blum v. Hillsboro, 49
Wis.2d 667, 671, 183 N.W.2d 47, 49 (1971)).
Recognizing the City's discretion to accept late bids will further the
City's ability to deal with problems in a sensible, practical way and thereby
enable the City to attain the statutory goals of preventing fraud and insuring
that the public receives the best work at the most reasonable price.
Power argues that other
jurisdictions have determined that late bids are not capable of
acceptance. These decisions are, of
course, cited only as persuasive authority.
We do not find them persuasive.
First, cases in other jurisdictions are based on statutes and rules
different from those in Wisconsin. For
example, in Rexton, Inc. v. State, 521 N.W.2d 51 (Minn. App.
1994), the Minnesota Court of Appeals held that where a courier responsible for
delivering a bid was delayed due to bad weather conditions and the bid was
therefore delivered one minute late, the lateness was a deficiency that could
not be waived at the state's discretion.
Id. at 53-54. The
court based its decision in part on a state rule requiring that late bids were
to be returned unopened. Id.
at 53. Power has cited no similar
Wisconsin rule that would indicate that our state has made a policy
determination that late bids are unacceptable.
Moreover, our courts
have recognized a city's power to exercise discretion in the bidding process
and the need to give cities the ability to deal with problems in a sensible,
practical way. See Envirologix
Corp. v. Waukesha, 192 Wis.2d 277, 291-92, 531 N.W.2d 357, 364 (Ct.
App. 1995); Waste Management, 84 Wis.2d at 470, 267 N.W.2d at
663-64. It is not this court's role to
impose restrictions on a city's discretion in the bidding process where the
legislature has been silent on the issue, as it has been in § 62.15, Stats.
If Power believes cities should not have the discretion to accept late
bids, it must look to the legislature for relief.
Contrary to the wishes
of the concurrence, our analysis of this case must end at this point. We will not address the standard by which a
court should review a city's exercise of discretion, or the point at which a city's
exercise of discretion should be overturned.
These issues were not raised or briefed on appeal and therefore, any
discussion on this issue would be nothing more than dicta.
By the Court.—Judgment
affirmed.
No. 95-0458(C)
MYSE, J. (concurring). The City of Bloomer's ability to ignore its
own bidding rules is the basis of this appeal.
The issue identified by the majority is whether the City has the power
to exercise discretion to accept an untimely bid. The majority without limitation has said that the City does have
such power and further speaks in language that implies that the City has the
power to disregard any of its bidding rules.
My answer to the limited question of whether the City has the power to
accept late bids is that it may, but only under limited circumstances. My answer to the broader question is that
the City has the power to ignore its own bidding rules only when the
noncompliance with the rule is not material and does not jeopardize the
integrity of the bidding process. See
Dillingham Constr., Inc. v. Milwaukee Metro. Sewerage Dist., 629
F.Supp. 406 (E.D. Wis. 1986).
In this case the bid was
received one and one-half hours late and under circumstances that provide some
assurance that the delay in submitting the bid did not provide an opportunity
for manipulation or alteration of the bid to the detriment of the other
bidders. Under these circumstances, if
it can be determined that the tardiness was not material and acceptance will
not compromise the integrity of the bidding process, the majority is correct in
deciding that the City has the power to exercise discretion to receive the
tardy bid. However, there must be a
judicial determination of whether these criteria are met in this case. The City does not have the power to ignore
the bidding rules it established if these criteria are not met. See id.
The majority does not
limit the power of the City to exercise its discretion, fails to establish
criteria upon which we review the City's exercise of discretion and does not
address whether the City properly exercised its discretion in this case. Without such limitations the majority
opinion throws open to the City's exercise of discretion all bidding rules. While one readily understands why the City
wished to accept a bid $80,000 lower than the timely bids that were submitted,
ability to obtain the lowest bid in its future lettings will be substantially
compromised if the rules of bidding are not meaningful and enforced so as to
create a level playing field for all participating in the bidding process. I fear that the broad language, the lack of
limitation and the lack of a standard to review the City's exercise of
discretion all invite mischief that will seriously compromise the legitimacy of
the bidding process.
[1] Affidavits were submitted to the trial court to explain the reasons behind Hooper's late bid. The affidavits reveal that Hooper's bid was prepared, placed in a sealed envelope and picked up by a courier service on Friday, December 9, for transport from Madison to Bloomer. The bid was to be delivered to the office of the city clerk no later than noon on Monday, December 12. While en route to Bloomer on December 12, the delivery truck broke down and was delayed until a replacement truck arrived. The courier service contacted the City and advised that the delivery on behalf of Hooper would be late. The delivery was ultimately made at 2:30 p.m.
[2] Power has not appealed other causes of action alleged and dismissed with prejudice along with the rest of the complaint. Therefore, we do not consider these issues. See Waushara County v. Graf, 166 Wis.2d 442, 451, 480 N.W.2d 16, 19 (1992) (it is a well-established rule in Wisconsin that appellate courts need not and ordinarily will not consider or decide issues that are not specifically raised on appeal).
[3] However, Power acknowledges that no Wisconsin case has addressed a city's authority to accept a late bid.
[4] Power cites City of Atlanta v. J.A. Jones Constr. Co., 392 S.E.2d 564 (Ga. App. 1990), rev'd, 398 S.E.2d 369 (Ga. 1990), vacated on remand, 402 S.E.2d 554 (Ga. App. 1991); Rexton, Inc. v. State, 521 N.W.2d 51 (Minn. App. 1994); Petri v. Montana State Univ., 860 P.2d 154 (Mont. 1993); George A. Nole & Son, Inc. v. Board of Educ., 514 N.Y.S.2d 274 (N.Y. A.D. 1987); H.R. Johnson Constr. Co. v. Board of Educ., 241 N.E.2d 403 (Ohio Com.Pl. 1968).
[5]
In State ex rel. Hron Bros. v. Port Washington, 265 Wis.
507, 509-10, 62 N.W.2d 1, 2 (1953), our supreme court, interpreting § 62.15, Stats., stated that when the powers
conferred on a municipal body involve the use of discretion, the courts will
not question its exercise except for an abuse equivalent to fraud. Furthermore, the court stated: "[W]hen the authority conferred was to
let the contract to the lowest responsible bidder the courts very
properly hold that the power thus conferred implies the exercise of discretion
which will not be interfered with by the courts." Id. at 510, 62 N.W.2d at 2
(emphasis in original). While these
statements suggest a city's exercise of discretion will be upheld absent
serious error, a more recent supreme court case indicates that judicial review
of bidding decisions is appropriate, although such review is "generally
limited to determining whether the bidding authority acted in an arbitrary or
unreasonable manner." Aqua-Tech,
Inc. v. Como Lake Protect. & Rehab. Dist., 71 Wis.2d 541, 550-51,
239 N.W.2d 25, 30 (1976).
Power has not pursued on appeal its initial claim that the City, if it had the discretion to accept the late bid, abused its discretion in doing so. Therefore, we need not determine whether the appropriate standard of review of the City's exercise of discretion is whether there was an abuse equivalent to fraud, as suggested by Hron, or whether the City acted in an arbitrary or unreasonable manner, as suggested by Aqua-Tech. However, we note the apparent inconsistency in these two cases to recognize that this issue may arise in the future.
[6] Because Power has not pursued on appeal its claim that the City abused its discretion, we need not address the circumstances under which a city may reasonably exercise its discretion, if one concluded that is the appropriate standard of review (see supra text accompanying note 5). However, we note that one federal court in Wisconsin has examined this issue as it relates to § 66.904(2)(c), Stats., a bidding statute for metropolitan sewerage districts. Dillingham Constr., Inc. v. Milwaukee Metro. Sewerage Dist., 629 F. Supp. 406 (E.D. Wis. 1986). In Dillingham, the district court concluded that the district had properly exercised its discretion when it accepted a bid in which the party had failed to fill in the amount of a penalty bond. Id. at 410. The court reasoned that acceptance of the bid was appropriate because the party's failure was not material and was quickly cured. Id. One could argue that under the reasoning in Dillingham, a reviewing court should examine whether a party's noncompliance with bidding rules was material in order to determine whether there was an unreasonable exercise of discretion, not to determine whether a city has the discretion to accept noncomplying bids.