COURT OF APPEALS DECISION DATED AND RELEASED September 27, 1995 |
NOTICE |
A party may file with the
Supreme Court a petition to review an adverse decision by the Court of
Appeals. See § 808.10 and
Rule 809.62, Stats. |
This opinion is subject to
further editing. If published, the
official version will appear in the bound volume of the Official Reports. |
No. 94-3227
STATE
OF WISCONSIN IN COURT OF
APPEALS
DISTRICT II
RICHARD ZEININGER and
URSULA ZEININGER,
Plaintiffs-Appellants,
v.
AFFORDABLE BUILDERS OF
WISCONSIN, INC., PETER
VANDER WIELEN and
SUSANN VANDER WIELEN,
Defendants-Respondents.
APPEAL from an order of
the circuit court for Winnebago County: ROBERT A. HAWLEY, Judge. Affirmed.
Before Anderson, P.J.,
Brown and Snyder, JJ.
BROWN, J. After
protracted litigation involving the construction of a house, the builder agreed
to buy it back to settle the claim. The
homeowners, Richard and Ursula Zeininger, agreed that this settlement could be
subject to the construction firm's ability to obtain financing. On the last day of the financing period, a
letter was delivered to the Zeiningers indicating that the construction firm's
owners, Peter and Susann Vander Wielen, had obtained the necessary loan. The Zeiningers claim that the notice of
financing was defective under the law governing real estate purchase
contracts. We hold, however, that the
overall transaction was dominated by the agreement to settle the lawsuits and
that the notice was sufficient. We
therefore affirm the trial court's order that the terms of the settlement be
specifically performed.
In May 1992, the
Zeiningers entered into a contract with Affordable Builders of Wisconsin, Inc.,
the Vander Wielens' construction firm.
The deal required Affordable Builders to build a home to specifications
set by the Zeiningers. The project was
finished in about ten weeks, near the end of July.
The Zeiningers
apparently were dissatisfied with the work, and in May 1993, they brought suit
against Affordable Builders and Peter Vander Wielen alleging that the house was
negligently constructed. The Zeiningers
subsequently amended their claim to include Susann Vander Wielen and to add
allegations that she misrepresented the time needed for construction. The Vander Wielens, in turn, responded with
claims of their own. They alleged that
the Zeiningers had failed to meet the payment schedule set out in the
construction contract.
During the course of
discovery and pretrial scheduling, the court ordered the parties to try
mediation.[1] This move met with success and the parties
entered into a settlement agreement on September 13, 1994.
The settlement agreement
had two main parts. The terms
pertaining to the real estate transfer, including the financing provision, were
set out on a standardized WB-11 “Residential Offer to Purchase.” Here, Affordable Builders agreed to buy the
house back from the Zeiningers for $102,300.
This document, however, referenced an attachment which set out the terms
for settling the litigation involving the Zeiningers, Affordable Builders and
each of the Vander Wielens.[2] Nevertheless, the financing provision is at
the focus of this appeal.
The financing
contingency provided the Vander Wielens with thirty days to obtain a
variable-rate loan for the full purchase price at a rate for the first year not
to exceed 9.5%. If they could not get a
financing commitment within this time frame, the Zeiningers had the option to
terminate the agreement.
After business hours on
Friday, October 13, the last day of the financing period, a letter from
Transamerica Financial Services was slipped through the mail slot of the
Zeiningers' attorneys. It stated:
To whom it may concern:
The loan applied for by Mr. and Mrs. Pete
Van Der Wielen [sic] has been approved at Transamerica Financial Services,
subject to us receiving a valid title with proper closing at Evans Title
Company in Appleton, WI.
This approval is valid until 11/30/94.
Nonetheless,
on Monday morning the Zeiningers, through their attorney, sent a facsimile
(followed by a letter) to the Vander Wielens' attorney invoking their right to
cancel because they did not receive sufficient notice of financing within the
thirty-day limit.
In November, the Vander
Wielens[3]
moved for an order compelling enforcement of the settlement agreement. The Zeiningers raised several arguments
before the trial court attempting to show that the agreement had been properly
terminated. Each pertained to specific
details of the standardized purchase agreement which they claimed had not been
fulfilled. See, e.g., Woodland
Realty, Inc. v. Winzenried, 82
Wis.2d 218, 223-24, 262 N.W.2d 106, 109 (1978). We will review each of these charges seriatim.
Before embarking on our
analysis, it is important to emphasize that this appeal concerns the
interpretation of a settlement agreement, not a garden-variety real
estate purchase agreement.[4] In either case, we are guided by contract
law. See Fleming v.
Threshermen's Mut. Ins. Co., 131 Wis.2d 123, 132, 388 N.W.2d 908, 911
(1986). However, when reviewing the
particular circumstances here presented, we may relax the rules of
interpretation to give force to the important policy of encouraging extra-judicial
settlement of disputes. See Radlein
v. Industrial Fire & Casualty Ins. Co., 117 Wis.2d 605, 622, 345
N.W.2d 874, 883 (1984); Peiffer v. Allstate Ins. Co., 51 Wis.2d
329, 337-38, 187 N.W.2d 182, 185-86 (1971).
Nonetheless, interpretation of a settlement agreement presents a
question of law which we review de novo.
See Borchardt v. Wilk, 156 Wis.2d 420, 427, 456
N.W.2d 653, 656 (Ct. App. 1990). With
these principles in hand, we now turn to the specific issues here raised.
The Zeiningers first
contend that the financing provision was not fulfilled because the
eleventh-hour notice named “Mr. and Mrs. Pete Van Der [sic] Wielen” and made
absolutely no reference to Affordable Builders. They then cite several cases which all emphasize the important
policy of keeping a corporation distinct from its shareholders. See, e.g., Stebane Nash Co. v.
Campbellsport Mut. Ins. Co., 27 Wis.2d 112, 121-22, 133 N.W.2d 737,
743-44 (1965). They seem to suggest
that finding this notice defective because it did not indicate that “Affordable
Builders” had obtained the loan will serve this goal.
We do not accept the
Zeiningers' legal policy arguments because the record indicates that both
Affordable Builders and each of the Vander Wielens were within the scope of the
settlement agreement. While Peter
signed the purchase offer as president of Affordable Builders, other sections
of the settlement agreement make clear references to both Peter and Susann as
individuals. We conclude, therefore,
that this alleged defect was not substantial enough to controvert the purpose
of the financing provision; that is, give the Vander Wielens (and their
construction firm) some time to obtain financing so that they could buy the
troubled house and bring an end to the litigation. See Borchardt, 156 Wis.2d at 427, 456 N.W.2d
at 657.
The Zeiningers next
argue that the Vander Wielens' financing commitment was defective because it
was only valid through November 30, 1994, while the settlement agreement
specified that closing would not occur until at least December 13, 1994. The trial court dismissed these concerns
reasoning that the parties would likely make an appropriate adjustment in the
closing date.
Nevertheless, the
Zeiningers claim that the validity of the settlement agreement should not turn
on “[t]he possible happening of future events.” However, they overlook the current factual record. A submission from the Vander Wielens' lender
indicates that the closing date problem could be easily circumvented by closing
the loan in November, but leaving the funds in escrow with the title
company. The Vander Wielens also
submitted an executed agreement between themselves and the title company which
would allow this second transaction to go forward.
Although the Zeiningers
stress that there was no indication that the Vander Wielens would be able to
secure these secondary commitments at the time the notice of financing was
delivered, they fail to present any evidence demonstrating how they were
negatively affected. We do not believe
that this minor flaw, in and of itself, is sufficient grounds for upsetting the
settlement. The financing contingency
served only to protect the Vander Wielens should they not be able to get a
loan. Once they approved, and sent
notice to the Zeiningers, they signaled their intent to carry out the main
element of the settlement, that is, to buy the house back.
Similarly, the
Zeiningers also complain that the financing terms that the Vander Wielens
actually secured did not meet the specifications laid out in the settlement. But they still fail to demonstrate how they
were adversely affected. In substance,
the settlement agreement required the Vander Wielens to buy the house for
$102,300, contingent only on their ability to obtain a variable rate loan not
to exceed 9.5% for the first year. The
lender, however, gave the Vander Wielens access to $115,000 at a fixed rate of
14%. As the Zeiningers illustrate, the
actual loan subjects the Vander Wielens to monthly payments several hundred
dollars more than the maximum they were willing to accept under the settlement
agreement.
We acknowledge that
these differences could be described as “material deviations” in a common real
estate purchase agreement. See Woodland
Realty, 82 Wis.2d at 224, 262 N.W.2d at 109. Nevertheless, the Zeiningers have not demonstrated how the Vander
Wielens' acceptance of stiffer loan terms affected their ability to sell the
house at the $102,300 price specified in the settlement agreement.
The Zeiningers' final
argument is that the after-hours delivery of the financing commitment was not
timely. The procedure outlined in the
standardized purchase form required the Vander Wielens to physically deliver a
document evidencing that they had obtained the necessary financing before
thirty days had expired. Even after
thirty days, the deal was not dead until the Zeiningers delivered written
notice informing the Vander Wielens that they were terminating the
contract. Here, the Zeiningers point to
a facsimile sent to the Vander Wielens early the following Monday in which they
officially noticed their intent to terminate the purchase agreement. However, the language of the letter itself
demonstrates that they were fully aware that the Vander Wielens had obtained the
needed financing.
The letter describes how
the notice delivered that prior Friday “hardly fulfills the requirements of the
Offer to Purchase ¼. It hardly constitutes a financing commitment
at all.” However, the Zeiningers have
not provided a factual basis demonstrating the cause of their confusion, nor
have they shown how the Vander Wielens' slipshod delivery affected their
ability to dispose of the house at the agreed price. As a result, after reviewing the affidavits and other record
material submitted by the parties, we conclude that the letter delivered to the
Zeiningers late Friday afternoon was a loan commitment under the terms of the
settlement agreement.
Since the Zeiningers
have failed to present any factual basis suggesting that the terms of the
settlement agreement have not been satisfied, we conclude that the Vander
Wielens are entitled to pursue the rights afforded them under the
agreement. We therefore affirm the
trial court's order compelling the Zeiningers to fulfill the terms of this
settlement agreement.
By the Court.—Order
affirmed.
Not recommended for
publication in the official reports.
[1] The trial court acted pursuant to § 802.11(1)(m), Stats., which grants the court general authority to enter pretrial orders which “may aid in the disposition of the action.” We applaud the trial court's effort to facilitate an out-of-court settlement and note that § 802.12(2), Stats., endows the trial court with specific authority to order “alternative dispute resolution.”
[2]
The agreement set out in the attachment provided, in relevant part:
The parties hereto acknowledge that Affordable Builders of Wisconsin, Inc. is offering to purchase the Zeininger's home as a compromise to ¼ [the lawsuit]. Richard Zeininger, Ursula Zeininger, Affordable Builders of Wisconsin, Inc., Peter Vander Wielen and Susann Vander Wielen do hereby agree that if the Zeiningers accept ¼ [their offer] and if this sale is consummated, ¼ [the lawsuit], including all claims and counterclaims therein, shall be dismissed, with prejudice to all parties, without costs to any party ....
[3] The record demonstrates that there has been some confusion about who comprises the defending parties. Although “Affordable Builders of WI, Inc.” was specifically named as the party bringing the motion, the trial court's subsequent order refers to the “defendant Affordable Builders of Wisconsin, Inc.” and to the “defendants” who presumably include both Affordable Builders and each of the Vander Wielens. The Zeiningers' argument concerning this issue and our substantive conclusion are set out in the body of the opinion.
[4] We thus dismiss the Zeiningers' concern that our analysis may set dangerous precedent because it will affect the manner in which the standard WB-11 “Residential Offer to Purchase” is interpreted. As explained above, our analysis is tempered because we are faced with a settlement agreement. This was not an arm's-length, market transaction. While a standardized form was used to lay out some of the terms, it specifically referenced a separate attachment which operated to dismiss the suit upon consummation of the sale. This latter provision expressed the primary reason why the Vander Wielens made the purchase offer (that is, to settle the lawsuit) and thus dominated the overall transaction.