COURT OF APPEALS DECISION DATED AND RELEASED September 12, 1996 |
NOTICE |
A party may file with the
Supreme Court a petition to review an adverse decision by the Court of
Appeals. See § 808.10 and
Rule 809.62, Stats. |
This opinion is subject to
further editing. If published, the
official version will appear in the bound volume of the Official Reports. |
No. 94-2242
STATE
OF WISCONSIN IN COURT OF
APPEALS
DISTRICT I
RENEE MEEKS, d/b/a
MILWAUKEE DISPATCH
SERVICE,
Plaintiff-Respondent,
v.
MICHELS PIPE LINE
CONSTRUCTION, INC.,
a Wisconsin
Corporation,
and ST. PAUL FIRE
& MARINE INSURANCE COMPANY,
d/b/a ST.
PAUL/SEABOARD, a Foreign Corporation,
Defendants-Appellants.
APPEAL from a judgment
of the circuit court for Milwaukee County: JOHN B. DANFORTH, Reserve
Judge. Reversed and cause remanded.
Before Wedemeyer, P.J.,
Fine, J., and Michael T. Sullivan, Reserve Judge.
PER CURIAM. Michels Pipe Line Construction, Inc., and
St. Paul Fire & Marine Insurance Company, appeal from a judgment awarding
Renee Meeks, d/b/a Milwaukee Dispatch, damages against Michels Pipe Line for
breach of contract and breach of duty of good faith and fair dealing, and
against St. Paul for its liability on a payment bond St. Paul issued on Michels
Pipe Line's behalf. We conclude the trial
court erred by not granting Michels Pipe Line and St. Paul's motion for summary
judgment dismissal. Accordingly, we
must reverse and remand the matter to the trial for resolution consistent with
this opinion.[1]
I.
Background.
Meeks owned a trucking
business that leased trucks and obtained trucks and drivers to work on jobs she
procured. In 1990, the Milwaukee
Metropolitan Sewerage District opened public bids on a project known as the
North Shore 6 Collector System Project (NS-6).
Among other things, the bid documents specified contractual requirements
and goals that the prime contractor to be awarded the bid had to meet. Michels Pipe Line was one of the bidders on
this project.
In preparation of its
bid, Michels Pipe Line contacted Meeks and other potential subcontractors. Meeks responded to the inquiry with what
turned out to be the low bid—she proposed that her company would perform the
trucking for the proposed contract at an hourly rate of $35 for tri-axle and
$37 for quad-axle dump trucks.
Michels Pipe Line then
sent Meeks a subcontractor form, which requested information including the
firm's status as a small, woman or minority owned business enterprise
(S/W/MBE). Meeks filled in the form,
acknowledging her S/W/MBE status, and returned it to Michels Pipe Line, which
in turn filled in the type of service Meeks was providing and the dollar amount
of the service provided both in actual dollars and the percentage of Michels
Pipe Line bid price expected to be awarded to Meeks. The form stated Meeks was expected to be paid $98,772, or 2.41%
of the bid price, for her trucking service.
The Sewerage District
eventually awarded Michels Pipe Line the NS-6 project as prime contractor. Michels Pipe Line then sent a purchase
order, dated January 21, 1991, to Meeks that specified the hourly trucking
rates proposed by Meeks and the dates of her contract would be “as called for.”[2]
Construction work on the
project was to commence in March or April 1991, but was delayed by, among other
things, a strike at a pipe supplier.
Construction eventually began and Meeks provided her trucking
service. In February 1992, a Michels
Pipe Line employee, Robert Downs, filed a grievance against his employer with
the Teamster's Union. Downs alleged
that he had been laid off by Michels Pipe Line, but that the company continued
to use S/W/MBE subcontractors. He
alleged that this violated the Sewer, Tunnel, Water and Utilities Agreement
between the Teamsters Local 200 and the Wisconsin Underground Contractors
Association (WUCA). This agreement
provided that an “employer may hire additional trucking when his equipment and
his own employees are fully employed.”
Downs sought back pay and reinstatement.
Michels Pipe Line
defended its actions by stating that it had hired S/W/MBE subcontractors to
work on public works projects and that it could not rehire Downs. In a closed session hearing, the Union and
WUCA reached an agreement that became the arbitrator's decision in the
case. The decision stated only that
Michels Pipe Line had to pay Downs $1,500 in settlement of the grievance and
that the settlement would not affect any unemployment compensation he received.
Downs was reinstated the
day after the grievance hearing; he began working at two sites—including the
NS-6 project. Meeks continued to work
at the project for another five months, at which time Michels Pipe Line
informed her that her company's services would no longer be needed.
Meeks billed Michels
Pipe Line throughout her time at the project and she was paid nearly $62,000;
this was the full amount for the actual work she performed. After she was terminated at the project, she
billed Michels Pipe Line for $37,490, the approximate difference between what
she had been paid and Michels Pipe Line's estimate of her company's total
expected services; that is, $98,772.
Michels Pipe Line decline to pay her, informing her by letter that her
company had been contracted on an hourly basis and that her company had been
paid in full for her work.
Meeks then contacted the
Sewerage District and spoke with its contract compliance officer, Paul
Wechter. Wechter then contacted William
Weltin, a vice president at Michels Pipe Line involved with the NS-6 Project,
to ascertain why Meeks's company had not been used to the full extent in the
initial bid. By telephone, Weltin
informed Wechter that due to Downs's grievance and the obligation to rehire
him, Michels Pipe Line was unable to use Meeks's company for the full amount
estimated. Wechter's department manager
informed Wechter that Michels Pipe Line's reason for under-utilization of
Meeks's company constituted good cause for substitution. The Sewerage District informed Meeks that
Michels Pipe Line's substitution had been approved; Wechter also wrote to
Michels Pipe Line for documents to substantiate the company's position. Michels Pipe Line sent the Sewerage District
the minutes from the grievance panel hearing on Downs's complaint.
Meeks filed suit against
Michels Pipe Line and St. Paul, alleging, inter alia, that she was
entitled to the full $98,772, regardless of the amount of work her company
performed on the project. Michels Pipe
Line and St. Paul moved for summary judgment dismissal, arguing first that
Meeks was not a third-party beneficiary to its contract with the Sewerage
District, and further, that even if Meeks were a third-party beneficiary, the
contract between Michels Pipe Line and the Sewerage District stated that it
could be changed with the District's approval.
They argued that because there was no genuine question of material fact
over whether the District had approved Meeks's substitution, summary judgment
dismissal should be granted.
The trial court, the
Hon. Michael Skwierawski presiding, orally ruled at the summary judgment
hearing that Meeks was a third-party beneficiary to the contract, and that
there was a genuine issue of material fact whether Meeks's services were
improperly substituted because Michels Pipe Line had made false representations
to the Sewerage District over the reinstatement of Downs. No written order was entered memorializing Judge
Skwierawski's ruling. Hence, when the
case went to trial before Reserve Judge John Danforth, he was uncertain over
the extent of the earlier summary judgment ruling.
The case went to trial
and the special verdict asked the jury whether Michels Pipe Line had a lump sum
contract with Meeks and whether Michels Pipe Line breached any obligation to
Meeks. The jury found that no lump sum
contract existed, but it did find that Michels Pipe Line had breached a duty to
Meeks and awarded her $27,500 in damages.
Michels Pipe Line and St. Paul now appeal from the judgment entered on
that verdict.
II.
Analysis.
We conclude that the
dispositive issue raised by Michels Pipe Line and St. Paul is whether the trial
court improperly denied their request for summary judgment dismissal of Meeks's
suit. We conclude that there were no
genuine issues of material fact in conflict at the time of the summary judgment
motion—the materials clearly show that Michels Pipe Line properly substituted
Meeks's services and that the Sewerage District approved this change in the
contract. Therefore, Meeks's suit was
not viable and should have been dismissed.
“Summary judgment is
appropriate to determine whether there are any disputed factual issues for
trial and `to avoid trials where there is nothing to try.'” Caulfield v. Caulfield, 183
Wis.2d 83, 91, 515 N.W.2d 278, 282 (Ct. App. 1994) (citation omitted). When we review a motion for summary
judgment, we apply the same methodology as the trial court, but we do not accord
the trial court's conclusion any deference.
Kotecki & Radtke, S.C. v. Johnson, 192 Wis.2d 429,
436, 531 N.W.2d 606, 609 (Ct. App. 1995).
The methodology is oft repeated:
[W]e first examine the pleadings to
determine whether they state a claim for relief. If the pleadings state a claim and the responsive pleadings join
the issue, we then must examine the evidentiary record to analyze whether a
genuine issue of material fact exists or whether the moving party is entitled
to judgment as a matter of law. Further,
“[o]n summary judgment, we must draw all justifiable inferences in favor of the
non-moving party, including questions of credibility and of the weight to
accorded particular evidence.”
Bay
View Packing Co. v. Taff, 198 Wis.2d 654, 674, 543
N.W.2d 522, 529 (Ct. App. 1995) (citation omitted).
The trial court decided
that Meeks was a third-party beneficiary of the contract between Michels Pipe
Line and the Sewerage District. The
parties disputed at summary judgment whether Meeks was as a matter of law a
third-party beneficiary to the contract.
The parties renew this dispute on appeal. We need not decide this issue to resolve the appeal; we assume
for purposes of summary judgment that Meeks was a third-party beneficiary. See id. at 529
(citation omitted).
The crux of this case is
whether genuine issues of material fact existed for Meeks's substitution under
the contract. Meeks argued that
questions of fact remain whether Michels Pipe Line misrepresented to the Sewerage
District the Downs's grievance panel determination that Michels Pipe Line
reinstate Downs, thereby justifying Meeks's substitution. Our review of the summary judgment materials
shows that no genuine issues of material fact existed and that the trial court
erred when it denied Michels Pipe Line and St. Paul's motion for summary
judgment.
The summary judgment
materials provide the following information.
Weltin, a Michels Pipe Line vice president, stated in his uncontroverted
affidavit that because of the Downs's grievance decision, Michels Pipe Line had
to reinstate Downs and therefore was unable to utilize Meeks's trucking service
as originally planned. He further
stated:
As a result of the unforeseen occurrence
involving Downs'[s] grievance, Michels sought and obtained MMSD's approval for
the change in the utilization of Meeks'[s] trucking services pursuant to the
terms of its agreement with MMSD.
Meeks
asserted that Michels Pipe Line had fraudulently obtained the Sewerage
District's approval because the minutes of the Downs's grievance hearing
discussed only a cash settlement with Downs, not a requirement that Michels
Pipe Line reinstate Downs. Meeks is
correct that the transcripts of the hearings in the summary judgment materials
do not mention Downs's reinstatement.
Michels Pipe Line, however, provided affidavits from those present at
the hearing, all of whom stated that the grievance arbitrators required Michels
Pipe Line to reinstate Downs. Meeks
provided nothing in the summary judgment materials to dispute these affidavits.
We also see no genuine
issues of material fact surrounding the Sewerage District's approval of Michels
Pipe Line's substitution of Meeks.
Wechter, the District's contract compliance officer, averred that verbal
assurance from prime contractors on the reasons for the contractors'
non-compliance with a contract is a necessary accommodation to demands of a
project such as the one at issue here.
Thus, nothing was unusual in the procedure used by Michels Pipe Line to
substitute Meeks. The contract allowed
for such a change with the approval of the District. The District did approve the substitution; this approval was sent
to Meeks.
In sum, although the
contract and subcontract listings were quite detailed and lengthy, under the
summary judgment materials present at the time of the summary judgment motions
there were no genuine issues of material fact surrounding Meeks's causes of
action. The materials clearly defeat
all of her claims; there was no way she could prevail under any
circumstance. See Barillari
v. City of Milwaukee, 194 Wis.2d 247, 256, 533 N.W.2d 759, 762
(1995). The trial court erred when it
denied Michels Pipe Line and St. Paul's motion for summary judgment
dismissal. Accordingly, we reverse the
judgment and remand the matter to the trial court for resolution consistent
with this opinion.
By the Court.—Judgment
reversed and cause remanded.
This opinion will not be
published. See Rule 809.23(1)(b)5, Stats.
[1] Several other issues are raised by Michels Pipe Line and St. Paul that we need not address because we reverse on the summary judgment issue. See Gross v. Hoffman, 227 Wis. 296, 300, 277 N.W. 663, 665 (1938) (only dispositive issue need be addressed).
[2]
The contract between Michels Pipe Line and the Sewerage District
provided in relevant part:
It is the policy of the Owner to
insure that small, women's and minority business enterprises be allowed the
maximum feasible opportunity to compete on district construction contracts.
The Owner has established a
system of minimum participation goals for construction contracts. These goals are as follows:
....
Women Business Enterprise2% of
contract or
Involvement Goalcontract as
modified
amount.
Small Business Enterprise 5% of
contract or
Involvement Goal contract as modified
amount.
Any bidder is required to make
good faith efforts to meet the percentage participation goals established on
the contract and to make good faith efforts to include small, women's and
minority businesses in their bid or proposal to the maximum extent possible.
Further, Michels Pipe Line signed a Subcontractor Listing which stated,
in part:
The Bidder
certifies that the firms identified on each subcontractor listing will be
awarded subcontracts for the indicated portions of the work in the event the
Bidder is awarded the contract. The
bidder agrees that, after the opening of bids, no changes or substitutions in
the listing will be allowed without the written approval of the Owner. Requests for such changes or substitutions
shall be made in writing with appropriate documentation and reasons included.
Among instructions to
Michels Pipe Line included in the contract documents was one titled
“Certification.” The document included
a subsection titled “Substitution or Replacement,” which provided:
Requests for substitution or replacement of any firm that the bidder has listed for use to meet the small, women's and minority business enterprise provisions of this policy will not be granted after bid opening except for good cause established by the contractor. A lower price by the proposed substitute or replacement for the listed small, women's or minority business enterprise is not good cause. An increase of the quoted price in toto or on a per unit basis by the small, women's or minority business enterprise may be good cause, depending upon the circumstances. Inability to perform work on a subcontract can be good cause, depending upon the circumstances.