COURT OF APPEALS DECISION DATED AND FILED May 11, 2010 David
R. Schanker Clerk of Court of Appeals |
|
NOTICE |
|
|
This opinion is subject to further editing. If published, the official version will appear in the bound volume of the Official Reports. A party may file with the Supreme Court a petition to review an adverse decision by the Court of Appeals. See Wis. Stat. § 808.10 and Rule 809.62. |
|
APPEAL
from an order of the circuit court for
Before
¶1 PER CURIAM. Shawn and Thomas Heuring
appeal from an order granting summary judgment to MSA Professional Services,
Inc. and A-1 Excavating, Inc., government contractors accused of negligently
designing and constructing a street in the City of
BACKGROUND
¶2 Approximately eight years ago, the City hired MSA to review
the City’s sewer and water systems. MSA
recommended the City replace sanitary sewer pipeline beneath
¶3 The City has no engineering staff and does not design its own
construction projects. MSA has provided
those services for ten years, and was again hired to design the
¶4 MSA solicited bids from contractors in early 2006. The City hired A-1 as general contractor. MSA and A-1 acted under separate contracts with the City and had no contractual relationship with one another. A-1’s job was simply to complete the project according to MSA’s design. MSA acted as the liaison between A-1 and the City, ensuring the project proceeded as scheduled and in conformity with the approved plans. Any substantial changes during construction required city council approval. Even relatively minor changes that could potentially impact other aspects of the project were approved by the City’s Department of Public Works. The DPW was informed of all deviations from the plans, regardless of their significance.
¶5 A-1’s contract indicates the City planned to open
¶6 The Heurings commenced this action following an accident on
September 25, 2006. That afternoon, Shawn
Heuring stepped between two vehicles parked on
DISCUSSION
¶7 Whether a contractor is entitled to governmental immunity is
a question of law we review de novo. See Estate
of Brown v. Mathy Constr. Co., 2008 WI App 114, ¶6, 313 Wis. 2d
497, 756 N.W.2d 417. We also review a
grant of summary judgment de novo, applying the same standard as the circuit
court. See Green Spring Farms v.
Kersten, 136
¶8
¶9 The first element is satisfied by proof that the government
provided the contractor with reasonably precise specifications.
¶10 The undisputed evidence shows the City and the DOT approved reasonably precise specifications. A-1’s contract required it to place only the first two asphalt layers and specifically noted the DOT “will … place the final lift of asphalt (1 ¾ inches thick) on the mainline run of Granite Street and Silver Street from Sixth Avenue to the Montreal River.” The project was “substantially completed” not when the DOT placed the final asphalt lift, but when A-1 completed the second asphalt layer and the roadway was open to traffic. A design drawing labeled “Silver Street Typical Section” shows the exposed concrete curb rising one and three-quarters inches above two layers of asphalt and notes the “surface course,” or final asphalt layer, will be “done by others.” There is no evidence MSA and A-1 retained any discretion with respect to the number or thickness of asphalt layers or the height of the curb. All were identified, with precision, in the design documents approved by the City and the DOT.
¶11 Design drawings also indicate the precise traffic control and warning signs required, and their location, during each phase of construction. The drawings depict an aerial view of the construction zone and note the exact spot of each barricade, traffic control drum, light, and sign. Signs indicating stops, detours, road closures, no parking zones, and impending road work are among those required. No required signage warned of the exposed curb or indicated a trip hazard. Any argument that these drawings confer substantial discretion or lack specificity is implausible at best.
¶12 Nonetheless, the Heurings contest this element, though they
conceded it before the trial court.[3] They argue A-1’s contract vested it with
considerable discretion by directing it to “erect and maintain barricades and
signs as necessary.” We reject this
argument because the necessity of barricades and signs was, of course, dictated
by the detailed drawings previously described.
The Heurings also contend A-1’s contract, requiring “any excavations,
obstacles, or other hazards” to be fenced in, confers broad discretion that
defeats immunity. We also reject this
argument. The Heurings would have
government contracts list the precise nature and location of every single
obstacle, excavation site, or hazard requiring fencing. The government cannot provide this prophetic
guidance, and the “encyclopedic” contracts required to do so are
unnecessary. Estate of Brown, 313
¶13 The second element requires proof that the contractor conformed to the approved design. The record contains no dispute that the roadway was constructed according to the design specifications, and Shawn Heuring’s underlying negligence claim assumes that it was. In addition, Michael Swan, A‑1’s field superintendent, testified at deposition that the appropriate signs, construction barrels, detours, and barricades were in place each day. There is no evidence A-1 or MSA failed to comply with any design or safety requirement included in the summary judgment materials, nor that they engaged in any sort of extemporaneous deviation.
¶14 The Heurings, citing alleged inconsistencies in the testimony
of A‑1’s field manager, claim there is a factual dispute about whether
construction barrels remained on Silver Street after its opening. The Heurings fail to complete this argument
by identifying a source in the record obligating the contractors to continue
safety measures after substantial completion of the project. We will not search the voluminous record to
support the Heurings’ argument. See Grothe
v. Valley Coatings, Inc., 2000 WI App 240, ¶6, 239
¶15 Finally, immunity requires a showing that the contractor warned
the supervising governmental authority about possible dangers known to the
contractor but not to the government. The
Heurings ask us to infer from deposition testimony that “both A-1 and MSA
failed to warn the City of
A Our main concerns with [the lack of a final] lift there were snow plowing for the winter and ponding water over the long term for the life of the pavement. We have that edge exposed on a regular basis in projects, you know. When we’re paving often the contractors will leave or will have some other task to do, and the lip of concrete is exposed … or accessible to pedestrians on a regular basis, and it generally isn’t a problem.
….
Q Okay. Did you make any recommendations to the city or indicate to them that [the exposed curb] was a problem?
A No.
Q Why not?
A I didn’t think of it as a problem, I guess. … [E]very time we build a road, there’s a time, a period where … the concrete edge is exposed like that.
Martin’s
undisputed testimony indicates the contractors never considered the exposed
curb a danger to pedestrians. Moreover,
the City was already aware of the exposed curb lip from the designs and its own
decision to have the DOT place the final lift.
Consequently, there is no evidence the contractors “ignore[d their] duty
to the public and [withheld] information about dangers that the government
might not know about.”[4] See Estate of Lyons, 207
¶16 MSA
and A-1 also claim summary judgment is appropriate pursuant to Restatement (Second) of Torts § 384 (1965). Because we affirm on immunity grounds, we
need not reach this issue. See State
v. Castillo, 213
By the Court.—Order affirmed.
This opinion will not be
published. See Wis. Stat. Rule 809.23(1)(b)5.
[1] Silver Street was not paved until the
following spring. As MSA supervisor
Scott Martin testified, asphalt paving is temperature dependent, yet is the
final element of road construction.
Demand for asphalt contractors is highest in fall, but DOT regulations
prohibit paving after a certain date.
Scheduling delays forced the DOT’s contractor to apply a temporary
winter solution because it was unable to complete the final lift before the
DOT’s deadline. Such problems are common
in cold-air environments.
[2] All references to the Wisconsin Statutes are to the 2007-08 version unless otherwise noted.
[3] MSA and A-1 contend the Heurings’
concession implicates the forfeiture rule.
See State v. Hayes, 2004 WI 80, ¶21, 273
[4] Martin stated at deposition that, in hindsight, he now thought the curb represented a trip hazard. However, Martin’s ex post facto reflection cannot transform a danger unknown at the time of the accident to a known one. Martin’s undisputed testimony demonstrates neither MSA nor A-1 notified the City of the exposed curb lip because they did not consider it a danger and, in any event, the City already knew of its existence.