2009 WI App 126
court of appeals of
published opinion
Case No.: |
2008AP2604 |
|
Complete Title of Case: |
|
|
American Transmission Co., LLC,
Plaintiff-Respondent, v.
Defendant-Appellant. |
|
|
Opinion Filed: |
July 23, 2009 |
Submitted on Briefs: |
May 13, 2009 |
Oral Argument: |
|
|
|
JUDGES: |
Dykman, Vergeront and Peterson, JJ. |
Concurred: |
|
Dissented: |
|
|
|
Appellant |
|
ATTORNEYS: |
On behalf of the defendant-appellant, the cause was submitted on the briefs of Marcia MacKenzie, Dane County Corporation Counsel, and Leslie A. Hamilton, Assistant Corporation Counsel. |
|
|
Respondent |
|
ATTORNEYS: |
On behalf of the plaintiff-respondent, the cause was
submitted on the brief of Brady C. Williamson and David J. Giles of |
|
A nonparty brief was filed by Jennifer E. Nashold and
David A. Ludwig, |
2009 WI App 126
COURT OF APPEALS DECISION DATED AND FILED July 23, 2009 David
R. Schanker Clerk of Court of Appeals |
|
NOTICE |
|
|
This opinion is subject to further editing. If published, the official version will appear in the bound volume of the Official Reports. A party may file with the Supreme Court a petition to review an adverse decision by the Court of Appeals. See Wis. Stat. § 808.10 and Rule 809.62. |
|
Appeal No. |
|
|||
STATE OF |
IN COURT OF APPEALS |
|||
|
|
|||
|
|
|||
|
|
|||
American Transmission Co., LLC,
Plaintiff-Respondent, v. Defendant-Appellant. |
||||
|
|
|||
APPEAL
from a judgment of the circuit court for
Before Dykman, Vergeront and Peterson, JJ.
¶1 VERGERONT, J. This action for a declaratory
judgment arises out of a dispute between American Transmission Co., LLC, and
¶2 We conclude that in Wis. Stat. § 196.491(3)(i) the legislature has expressly withdrawn the power of municipalities to act, once the PSC has issued a certificate of public convenience and necessity, on any matter that the PSC has addressed or could have addressed in that administrative proceeding. We also conclude that the local power that is withdrawn by the statute includes requiring the application for local permits of the type that are in dispute in this case. Accordingly, we affirm the circuit court.
BACKGROUND
¶3 American Transmission proposed to build three separate
high-voltage transmission lines within
¶4 American Transmission involved
¶5 As soon as the PSC issued a certificate of public convenience
and necessity for the third project, American Transmission filed this action
seeking a judgment declaring that
DISCUSSION
¶6 On appeal
¶7 American Transmission responds that Wis. Stat. § 196.491(3)(i) plainly and expressly
preempts the local ordinances
¶8 We review de novo the
grant or denial of summary judgment, employing the same methodology as the
circuit court. Green Spring Farms v. Kersten,
136
¶9 Under the preemption doctrine, where a matter is of statewide
concern, local control must yield if:
(1) the legislature has clearly and expressly withdrawn the power
of municipalities to act; (2) the local regulation logically conflicts
with state legislation; (3) the local regulation defeats the purpose of
state legislation; or (4) the local regulation violates the spirit of
state legislation. DeRosso Landfill Co. v. City of
¶10 We agree with the circuit court and American Transmission that
there is preemption on the first ground—express withdrawal in Wis. Stat. § 196.491(3)(i) of the
power of municipalities to act. We
therefore do not address
¶11 Wisconsin Stat. § 196.491(3)(i)
provides: “If installation or
utilization of a facility for which a certificate of convenience and necessity
has been granted is precluded or inhibited by a local ordinance, the
installation and utilization of the facility may nevertheless proceed.” Because the supreme court in RURAL
v. PSC, 2000 WI 129, 239
¶12 In RURAL the Village of Rockdale opposed some of the conditions
the PSC imposed in a certificate of public convenience and necessity on the
ground that the conditions “had the effect of wrongfully excluding Rockdale
from its extraterritorial zoning authority over the Town of Christiana.” RURAL, 239
¶13 In arriving at this conclusion, the court in RURAL
stated that the “purpose of [Wis.
Stat. § 196.491(3)(i)] is clear on its face. Local ordinances, such as zoning ordinances,
cannot impede what has been determined to be of public convenience and
necessity.”
¶14
¶15
¶16
¶17 The soundness of the RURAL court’s approach is
illustrated in this case. Even if Dane
County intends to do nothing more than have American Transmission apply for
permits so that it can locally enforce what American Transmission is required
to do under the PSC orders, the permit process in itself is an additional
impediment or inhibiting factor in the installation and utilization of the
transmission lines. However, as we
understand
¶18 As did the court in RURAL, we emphasize that the PSC, in
conjunction with the DNR, is charged with considering environmental factors and
land use and development plans for the area of the project. Wis.
Stat. § 196.491(3)(d)3., 4., 6.
In addition, we note that municipalities and towns receive notice of
applications for projects proposed to be located within their boundaries. Section 196.491(3)(a)1. Affected local governments may participate in
the PSC proceedings and may petition for review of the PSC decision in the
circuit court. See § 196.491(3)(j).
Indeed,
CONCLUSION
¶19 We conclude the circuit court properly construed Wis. Stat. § 196.491(3)(i) to expressly withdraw the power of municipalities to act, once the PSC has issued a certificate of public convenience and necessity, on any matter that the PSC has addressed or could have addressed in that administrative proceeding. The circuit court also properly concluded that the local power that is withdrawn by the statute includes requiring the application for local permits of the type that are in dispute in this case. Accordingly, we affirm the circuit court.
By the Court.—Judgment affirmed.
[1] All references to the Wisconsin Statutes are to the 2007-08 version unless otherwise noted.
[2] Wisconsin Stat. § 196.491(3) applies to all “facilities,” and a facility is defined as a “large electric generating facility or a high-voltage transmission line.” Section 196.491(1)(e).
[3]
[4] The PSC has filed an amicus brief arguing essentially the same view of the statute as that taken by the circuit court and American Transmission.
[5] Although
there may be discretionary aspects to a circuit court’s decision whether to
grant or deny declaratory relief, when the appropriateness of the court’s
decision depends upon a question of law, our review is de novo. See J.G. v. Wangard, 2008 WI 99, ¶18,
313
[6] Wisconsin Stat. § 196.491(3)(d) provides in part:
[T]he commission shall approve an application … for a certificate of public convenience and necessity only if the commission determines …:
….
3. The design and location or route is in the public interest considering alternative sources of supply, alternative locations or routes, individual hardships, engineering, economic, safety, reliability and environmental factors, except that the commission may not consider alternative sources of supply or engineering or economic factors if the application is for a wholesale merchant plant….
4. The proposed facility will not have undue adverse impact on other environmental values such as, but not limited to, ecological balance, public health and welfare, historic sites, geological formations, the aesthetics of land and water and recreational use….
….
6. The proposed facility will not unreasonably interfere with the orderly land use and development plans for the area involved.
[7] When
we construe a statute we give words their common meaning and we may use a
dictionary for this purpose. State
v. Sample, 215
While “inhibit” in
some contexts might have the meaning of “prevent,” “prohibit,” or “forbid,” in
the context of Wis. Stat. § 196.491(3)(i)
“inhibit” is an alternative to “preclude.”
According to