2009 WI App 30
court of appeals of
published opinion
Case No.: |
2007AP2673 |
|
Complete Title of Case: |
† Petition for Review filed |
|
Wisconsin Public Service Corporation,
Plaintiff-Respondent-Cross-Appellant, v. Patricia K. Andrews, † Defendant-Appellant-Cross-Respondent. |
|
|
Opinion Filed: |
February 24, 2009 |
Submitted on Briefs: |
November 4, 2008 |
|
|
|
|
JUDGES: |
|
|
|
|
|
|
|
Appellant |
|
ATTORNEYS: |
On behalf of the defendant-appellant-cross-respondent,
the cause was submitted on the briefs of Forrest O. Maki and Karry A. Johnson of Maki,
Ledin, |
|
|
Respondent |
|
ATTORNEYS: |
On behalf of the plaintiff-respondent-cross-appellant,
the cause was submitted on the briefs of Trevor J. Will and Leon W. Todd III of Foley
& Lardner LLP of |
|
|
2009 WI App 30
COURT OF APPEALS DECISION DATED AND FILED February 24, 2009 David
R. Schanker Clerk of Court of Appeals |
|
NOTICE |
|
|
This opinion is subject to further editing. If published, the official version will appear in the bound volume of the Official Reports. A party may file with the Supreme Court a petition to review an adverse decision by the Court of Appeals. See Wis. Stat. § 808.10 and Rule 809.62. |
|
Appeal No. |
|
|||
STATE OF |
IN COURT OF APPEALS |
|||
|
|
|||
|
|
|||
|
|
|||
Wisconsin Public Service Corporation, Plaintiff-Respondent-Cross-Appellant, v. Patricia K. Andrews, Defendant-Appellant-Cross-Respondent. |
||||
|
|
|||
APPEAL
and CROSS-APPEAL from a judgment of the circuit court for
Before
¶1 BRUNNER, J. Patricia Andrews appeals a summary judgment dismissing her counterclaims against Wisconsin Public Service Corporation (WPSC) in a declaratory judgment action. Andrews contends genuine issues of material fact exist on her counterclaims. WPSC cross-appeals a portion of the same judgment dismissing its claim for a declaratory judgment. WPSC argues the circuit court erroneously concluded that WPSC did not have the right to replace an existing transmission line with a new transmission line under existing easements.
¶2 We affirm the portion of the summary judgment dismissing Andrews’ counterclaims. However, we reverse the portion of the judgment dismissing WPSC’s claim for a declaratory judgment. On remand, we direct the circuit court to enter a declaratory judgment in WPSC’s favor.
BACKGROUND
¶3 In October 2001, WPSC obtained authority from the Wisconsin Public Service Commission to construct a high voltage, 345kV, transmission line from Arrowhead, Minnesota to Weston, Wisconsin. The Arrowhead-Weston transmission line’s approved path traverses Andrews’ property, where there is currently a 161kV transmission line.
¶4 The existing 161kV line sits on 105-foot-wide easements granted by Andrews’ predecessors in title. The easements were granted in two 1972 deeds and are now owned by WPSC. Under the 1972 deeds, WPSC has the “perpetual right, privilege and easement to construct, maintain and operate an electric transmission line, or lines which may be constructed or reconstructed at any time hereafter with the necessary poles, cross-arms, guys, braces, wires and appurtenances.”
¶5 In 2002, WPSC was preparing to construct the new transmission line and requested permission from Andrews to enter her property for surveying. Andrews refused to give permission and, through her attorney, disputed whether the current easements permitted construction of the new transmission line.
¶6 In April 2006, WPSC commenced this action seeking a declaratory judgment establishing its right to construct the new transmission line under the 1972 easements. WPSC moved for summary judgment, which the court denied. The court concluded WPSC’s easement rights were limited by the easements’ initial use for the 161kV transmission line. Therefore, the court concluded WPSC was required to obtain new easements complying with post-1972 statutory requirements applicable to high-voltage transmission line easements, specifically Wis. Stat. § 182.017(7)(a).[1]
¶7 Andrews filed a litany of counterclaims, on which WPSC also moved for summary judgment. Generally, Andrews’ counterclaims alleged WPSC acted tortiously by bringing the declaratory judgment action. She also alleged trespass and statutory and administrative code violations. The circuit court granted WPSC’s motion for summary judgment, dismissing Andrews’ counterclaims.
DISCUSSION
¶8 We review summary judgments de novo, applying the same
methodology as the circuit court. Park
Bancorporation, Inc. v. Sletteland, 182
I. WPSC’S CROSS-APPEAL
¶9 We first address the court’s dismissal of WPSC’s claim for a declaratory judgment, which is the subject of WPSC’s cross-appeal. WPSC contends the court erred when determining WPSC could not build the new transmission line under the 1972 easements, but was instead required to obtain new easements that complied with Wis. Stat. § 182.017(7)(a).
a. WPSC’S Easement Rights
¶10 A deed granting an easement defines the relative rights of the
landowners. Eckendorf v. Austin, 2000
WI App 219, ¶7, 239
¶11 The deeds granting the easements conveyed a “perpetual right, privilege and easement to construct, maintain and operate an electric transmission line, or lines which may be constructed or reconstructed at any time hereafter with the necessary poles, cross-arms, guys, braces, wires and appurtenances.” The width and location of the easements were also specified.
¶12 While the easement rights granted by the deeds are broad, they are not ambiguous. Because they are not ambiguous, there is no need to look beyond the deeds’ language. See id. The deeds’ language permits WPSC to construct or reconstruct transmission lines at any time. Because the Arrowhead-Weston line is a transmission line, its construction is plainly permitted under the deeds.
¶13 Absent ambiguity in the deeds, it was inappropriate for the
court to look outside the deeds, including at how the easements are currently
being used. See id. The court relied
primarily on Lehner v. Kozlowski, 245
The rule is well settled that where a
grant of an easement is general as to the extent of the burden to be imposed on
the servient tenement, an exercise of the right, with the acquiescence and
consent of both parties, in a particular course or manner, fixes the right and
limits it to the particular course or manner in which it has been enjoyed.
¶14 In Lehner, our supreme court addressed a written agreement
creating an easement for a drainage ditch, but not specifying the easement’s
location.
¶15 In addition to relying on Lehner, the circuit court’s decision
quoted Shellow v. Hagen, 9 Wis. 2d 506, 513, 101 N.W.2d 694 (1960) (“The
degree of definiteness of an easement is determined by the nature and extent of
the right asserted”), and Niedfeldt v. Evans, 272 Wis. 362,
365, 75 N.W.2d 307 (1956) (“The extent of the easement is commensurate with and
determined by the use.”). These cases
address prescriptive easements, which are inherently different from express
easements in that prescriptive easements are necessarily defined by prior
use. See
Shellow,
9
b. Applicability of Wis.
Stat. § 182.017(7)(a)
¶16 Having determined that WPSC was permitted to construct the new power lines under the 1972 easements, we next address the applicability of Wis. Stat. § 182.017(7)(a). Section 182.017(7) applies to right-of-way easements for high-voltage transmission lines, with § 182.017(7)(a) requiring:
The conveyance under
ch. 706 and, if applicable, the petition under s. 32.06(7), shall describe the
interest transferred by specifying, in addition to the length and width of the
right-of-way, the number, type and maximum height of all structures to be
erected thereon, the minimum height of the transmission lines above the
landscape, and the number and maximum voltage of the lines to be constructed
and operated thereon.
These requirements became
effective on September 30, 1975. 1975
¶17 The statute governs
what must be specified in a conveyance of an easement. Because the easements here were conveyed
prior to the enactment of the statute, the conveyances were not subject to the
statute’s requirements. The circuit
court’s conclusion that WPSC was required to obtain new easements complying
with Wis. Stat.
§ 182.017(7)(a) was premised on its erroneous conclusion that WPSC’s
easement rights were limited by the easements’ current use.
II. ANDREWS’ APPEAL
¶18 We next address Andrews’ appeal contesting the summary judgment dismissing her counterclaims. These counterclaims included: abuse of process; malicious prosecution; trespass; waiver and estoppel; violations of Wis. Stat. ch. 196; violations of Wis. Admin. Code § PSC 113.0508 (Apr. 2007); and entitlement to attorney fees and punitive damages.
a. Abuse of
Process
¶19 Andrews claims WPSC’s institution of the declaratory judgment
action against her constituted an abuse of process. Abuse of process is a tort that occurs when
someone “uses a legal process, whether criminal or civil, against another primarily
to accomplish a purpose for which it is not designed ….” Schmit v. Klumpyan, 2003 WI App 107,
¶6, 264
¶20 Andrews contends a jury could infer WPSC used the declaratory judgment action to end Andrews’ resistance to the new power line, exhaust her financial resources, and deter other easement owners from seeking compensation through condemnation. Andrews attempts to support her claim with the following deposition testimony: that Andrews was the only landowner to challenge WPSC’s rights under an existing easement; a WPSC employee did not know why Andrews was sued; an employee of a WPSC subcontractor did not know why Andrews was sued; and that time and money were considerations in suing Andrews. Andrews also contends WPSC’s actions were contrary to prior information it provided to landowners stating they would be compensated for easements for the new transmission line.
¶21 We conclude Andrews’ abuse of process claim cannot survive
summary judgment. A legitimate dispute
existed about WPSC’s rights under the 1972 easement, and a declaratory judgment
action was a proper means of resolving that dispute. Andrews points to no improper actions by WPSC
in prosecuting the declaratory judgment action.
See Brownsell, 102
b. Malicious
Prosecution
¶22 Andrews claims WPSC’s declaratory judgment action constituted
malicious prosecution.
¶23 Establishing malicious prosecution requires proof of six
elements: (1) there must have been a
prior institution or continuation of some regular judicial proceedings against
the plaintiff in this action for malicious prosecution; (2) such former
proceedings must have been by, or at the instance of, the defendant in this
action for malicious prosecution; (3) the former proceedings must have
terminated in favor of the defendant therein, the plaintiff in the action for
malicious prosecution; (4) there must have been malice in instituting the
former proceedings; (5) there must have been want of probable cause for the
institution of the former proceedings; and (6) there must have been injury or
damage resulting to the plaintiff from the former proceedings. Krieg, 104
¶24 The parties focus their arguments on whether there was malice and a lack of probable cause for the declaratory judgment action. However, given our decision on WPSC’s cross-appeal, there is no genuine issue of material fact on the third element of malicious prosecution, which here requires Andrews to prevail in the declaratory judgment action. Our decision renders WPSC, not Andrews, the prevailing party in that action. Therefore, Andrews cannot prevail on her malicious prosecution claim.
c. Trespass
¶25 Andrews claims WPSC trespassed on her property. Neither Andrews nor her husband witnessed anyone trespass on their property. Andrews instead relies on 2004 survey maps showing where the new transmission line would be built and argues the existence of these maps creates an inference that someone entered her property. WPSC submitted an affidavit stating the maps were created remotely using an elaborate process involving aerial photography and computer software.
¶26 The summary judgment record reveals no genuine issue of material fact on Andrews’ trespass claim. Given WPSC’s evidence that the survey maps were created without entering Andrews’ property, the survey maps cannot support an inference that WPSC entered Andrews’ property. By not presenting contradictory evidence, Andrews left undisputed WPSC’s averments about how the maps were created.
¶27 Additionally, under the easements’ language, WPSC had the right to maintain, construct, and reconstruct transmission lines on the easement. Surveying the property for the construction of a new transmission line would fit within WPSC’s broad rights under the easement and would not constitute trespass.
d. Waiver and Estoppel
¶28 Andrews claims WPSC “has abused its statutory condemnation privilege through its actions or inactions, and therefore has waived or otherwise lost its right to condemn her property based upon that abuse of privilege.” She similarly claims WPSC was estopped from condemning her property due to this declaratory judgment action.
¶29 Andrews raised these claims in a separate action attempting to
keep WPSC from condemning her property. See Andrews v. Wisconsin Public Serv. Corp.,
2009 WI App 6, ¶4, No. 2007AP2541. These
claims were rejected on summary judgment in that action, and we rejected those
claims on appeal.
e. Violation of Wis.
Stat. ch. 196
¶30 Andrews claims WPSC unjustly discriminated against her by bringing the declaratory action against her and not other landowners. She contends WPSC violated Wis. Stat. § 196.60(3):
If a public utility gives an unreasonable preference or advantage to any person or subjects any person to any unreasonable prejudice or disadvantage, the public utility shall be deemed guilty of unjust discrimination. A public utility violating this subsection shall forfeit not less than $50 nor more than $5,000 for each offense.
She contends she may bring this claim under Wis. Stat. § 196.64(1), which makes violations of Wis. Stat. ch. 196 privately actionable.
¶31 However, there is no genuine issue of material fact on this claim because there is no evidence that any other landowners were similarly situated to Andrews. There is no evidence about other landowners’ easements, nor is there any evidence that other landowners attempted to obstruct WPSC’s access to those easements. WPSC and Andrews disputed WPSC’s easements rights, and the declaratory judgment action was a legitimate means of ascertaining the parties’ rights.
f. Violation of Wis. Admin. Code § PSC 113.0508
¶32 Finally, Andrews claims WPSC violated Wis. Admin. Code § PSC 113.0508, which prohibits a utility from engaging in any oppressive or deceptive practices. Andrews claims WPSC violated § PSC 113.0508(5), which states a utility shall not “[c]laim or attempt to claim to enforce a right, with knowledge or reason to know that the right does not exist.”
¶33 Andrews’ claims WPSC knew, or had reason to know, it had no right to construct the new transmission line under the 1972 easements. She also relies on the fact that WPS did not actually own the easements when it commenced the declaratory judgment action, even though WPSC promptly obtained assignment of the easements upon learning of this fact.
¶34 We conclude there is no genuine issue of material fact on this claim. Pursuant to our decision on WPSC’s cross-appeal, WPSC did have the right to construct the new transmission line on the existing easements. Further, there is no evidence the easement ownership issue was anything other than an oversight that was promptly remedied.
g. Attorney Fees and Punitive Damages
¶35 Based on the alleged conduct underlying Andrews’ counterclaims, she claims she is entitled to attorney fees and punitive damages. Given our decision affirming the summary judgment dismissing her counterclaims, as well as our decision on WPSC’s cross-appeal, there is no basis for Andrews’ claim for attorney fees or punitive damages.
CONCLUSION
¶36 We affirm the portion of the judgment dismissing Andrews’ counterclaims. However, we reverse that portion of the judgment dismissing WPSC’s claim for a declaratory judgment regarding its rights under the easement. On remand, we direct the court to enter a declaratory judgment in WPSC’s favor.
By the Court.—Judgment affirmed in part; reversed in part and cause remanded with directions.