2009 WI App 24
court of appeals of
published opinion
Case No.: |
2008AP53 |
|
Complete Title of Case: |
†Petition for Review Filed |
|
Richard O. Becker and Jon O. Becker,
Plaintiffs-Respondents, v. Crispell-Snyder, Inc. and Continental Casualty Company,
Defendants-Appellants.† |
|
|
Opinion Filed: |
January 14, 2009 |
Submitted on Briefs: |
September 29, 2008 |
|
|
|
|
JUDGES: |
Brown, C.J., |
Concurred: |
|
Dissented: |
|
|
|
Appellant |
|
ATTORNEYS: |
On behalf of the defendants-appellants, the cause was
submitted on the briefs of W. Wayne Siesennop and Scott J. Thomsen of Siesennop & Sullivan of |
|
|
Respondent |
|
ATTORNEYS: |
On behalf of the plaintiffs-respondents, the cause was
submitted on the brief of Timothy S. Knurr of Schoone, Leuck, Kelley, |
|
|
2009 WI App 24
COURT OF APPEALS DECISION DATED AND FILED January 14, 2009 David
R. Schanker Clerk of Court of Appeals |
|
NOTICE |
|
|
This opinion is subject to further editing. If published, the official version will appear in the bound volume of the Official Reports. A party may file with the Supreme Court a petition to review an adverse decision by the Court of Appeals. See Wis. Stat. § 808.10 and Rule 809.62. |
|
Appeal No. |
|
|||
STATE OF |
IN COURT OF APPEALS |
|||
|
|
|||
|
|
|||
|
|
|||
Richard O. Becker and Jon O. Becker,
Plaintiffs-Respondents, v. Crispell-Snyder, Inc. and Continental Casualty Company,
Defendants-Appellants. |
||||
|
|
|||
APPEAL
from a judgment of the circuit court for
Before Brown, C.J.,
¶1 BROWN, C.J. This case presents the flip side of Sussex
Tool & Supply, Inc. v. Mainline Sewer and Water, Inc., 231 Wis. 2d
404, 605 N.W.2d 620 (Ct. App. 1999). Sussex
Tool held that the complainant’s business establishment was not a
third-party beneficiary to a road construction contract since it was only
incidentally located near the project like every other business on that
street.
¶2 Before
we set forth the facts, it is important to note that while many of the facts we
are about to relate were disputed, our review is limited to a search for any
credible evidence that will support the jury verdict. Heikkinen v. United Servs. Auto. Ass’n, 2006
WI App 207, ¶42, 296
¶3 This
dispute began in 2000 when the Beckers were considering whether to purchase
land in the town of
¶4 In
2001, after having made a substantial investment in the subdivision, the town
forced the Beckers to change engineers, telling them that they had to use
Crispell-Snyder—the town’s engineering firm for thirty years—or construction
was going to be shut down and the subdivision was not going to happen. The Beckers objected, but Morris assured them
that Crispell-Snyder’s fees would be within 1 to 2% of the Beckers’ choice of
engineers and that the extra 25% in their line of credit would not actually be
used. Based on these assurances, the
Beckers signed the developer’s agreement with the town, making it so.
¶5 After the Beckers signed the
agreement, construction was allowed to continue. Crispell-Snyder billed the town for its time
spent on the Beckers’ development, pursuant to its oral public works contract
with the town. All the while, the
agreement made the Beckers liable for Crispell-Snyder’s invoices.[1] The town simply withdrew the money from the
Beckers’ line of credit. It
approved every invoice, relying on Crispell-Snyder’s good faith to bill for
only reasonable and necessary services.
The Beckers voiced their objection to Morris, but he never
responded. The Beckers did not see the
invoices or have a chance to object to their payment until after the fact.
¶6 Crispell-Snyder’s
bills were high enough that the town ultimately withdrew all of the Beckers’
line of credit and sent them a bill for $177,392.22. The town also billed the Beckers about
$87,000 to settle a lawsuit involving the excavation contractor. The excavation contractor had claimed damages
because it had to do more work than it had bid on. The jury determined that Crispell-Snyder’s
engineering negligence led to this mistake.
The evidence showed that Crispell-Snyder put into the specifications an
incorrect quantity of earth to be removed.
¶7 The
Beckers sued Crispell-Snyder, claiming they were third-party beneficiaries to
the town’s contract with Crispell-Snyder.
Crispell-Snyder moved for summary judgment asserting that, as a firm of
engineering professionals, it was immune from suit. It also invoked the Sussex Tool case and
claimed that the Beckers, like the complainant in Sussex Tool, could not
claim third-party beneficiary status to its contract with the town. The circuit court ruled that Crispell-Snyder
waived its immunity claim by not raising it as an affirmative defense, and even
if it was not waived, public policy did not forbid the Beckers’ claim. It also held that the Beckers were
third-party beneficiaries. A trial was
held and a jury awarded damages to the Beckers, finding that Crispell-Snyder
completed more work than necessary, overcharged the Beckers for change orders
and negligently handled the excavator’s bid.
¶8 Crispell-Snyder
appeals, claiming that the Beckers are incidental—not
third-party—beneficiaries, that the jury had insufficient evidence to support
its verdict, and that common-law immunity or public policy bars the Beckers’
claims. We will address each, in turn.
Third-Party Beneficiary Status
¶9 A
party wishing to enforce a contract must either be a party to that contract or
a third-party beneficiary. See Schilling
v. Employers Mut. Cas. Co., 212
¶10 Crispell-Snyder
claims that the Beckers were not third-party beneficiaries because they failed to
show how the contract between the town and Crispell-Snyder directly and
primarily benefited them. The facts
regarding this particular issue are not in dispute and require applying the law
to the undisputed facts. Therefore, we
will review this claim de novo. See Szymczak
v. Terrace at St. Francis, 2006 WI App 3, ¶¶10-11, 289
¶11 A
third-party beneficiary is one who the contracting parties intended to “directly
and primarily” benefit. Winnebago
Homes, Inc. v. Sheldon, 29
¶12 Crispell-Snyder
claims that the facts here parallel Sussex Tool because this is a public
works contract with the primary purpose of ensuring that a public body, the
town, inherits infrastructure that meets its standards. In its opinion, the fact that the
infrastructure was in the Beckers’ development was only incidental. It asserts that the Beckers’ only benefit was
the same as the complainant’s in Sussex Tool—profit as a result of
the improvements, an incidental benefit at best.
¶13 In
Sussex
Tool, a village hired a contractor for a sewer project and the
contractor promised to provide vehicular access to properties affected by the project.
¶14 In
this case, the evidence of the oral contract between the town and
Crispell-Snyder is not specific enough for us to examine the parties’ intent
through specific express language.
However, we can use the totality of the circumstances to evaluate
whether the contract (1) specifically conferred a direct benefit on the
Beckers, (2) limited the benefit to a well-defined group of third parties, and
(3) required the contractor to assume liability to third parties. See Isaac v. Gerretson Co., 179
¶15 The
Beckers have met the first two factors based on facts establishing their
indispensability to the contract. The
town and Crispell-Snyder entered into the contract because the Beckers needed
an engineer to oversee their development.
The direct benefit to the Beckers, therefore, was engineering oversight,
not simply future possible profit. And,
the only other third party in the same situation as the Beckers was the
neighboring developer who also had to use Crispell-Snyder to oversee
construction. Thus, the Beckers have met
the first two factors.
¶16 The
third-party creditor-debtor relationship rule from Severson v.
¶17 The
Beckers have met all three factors found in Sussex Tool. Therefore, we hold that they were a
third-party beneficiary of the public works contract between the town and
Crispell-Snyder.
Sufficiency of the Evidence
¶18 The
jury found that Crispell-Snyder breached its contract with the town and awarded
the Beckers damages for three change orders, excess inspection fees, and the
excavator’s claim. After trial, the
court specifically approved the jury verdict and upheld it against
Crispell-Snyder’s postverdict motions, stating that the jury took their
“responsibility seriously” and “let [their] verdict speak the truth.”
¶19 Crispell-Snyder
argues that there is no evidence supporting a breach of contract; rather, the
evidence showed only that it completed “too much” work resulting in a higher
price. In its view, its work would have
had to be incomplete or defective before it could be called a breach. It also argues that there cannot be a breach
since the town never complained about its work and, moreover, all the work
performed was within the scope of the developer’s agreement.
¶20 The
jury is the ultimate arbiter of credibility, and appellate courts review
evidence in the light most favorable to the verdict. Roach, 73
¶21 At
trial, representatives of both contractual parties—Morris and Crispell-Snyder’s
manager in charge of the Beckers’ development—testified that implicit in the
contract was that Crispell-Snyder would bill for only “reasonable and
necessary” work. Therefore, the jury could
find a breach of contract if credible evidence showed, under any reasonable
view, that Crispell-Snyder billed for unreasonable or unnecessary work. And that is just what the jury found. Again, we reiterate that we will only set
forth the credible evidence supporting the verdict.
A. The Change Orders
¶22 Evidence
at trial showed that, under one reasonable view, Crispell-Snyder’s three change
orders were either unnecessary or unreasonable.
The Beckers testified that they objected to all three change orders but
felt, given the town’s ultimatum, they had no choice but to sign them.
¶23 The
first change order had to do with compaction of the roads prior to paving. To test compaction, a heavy truck runs over
the road and the road is visually inspected for deflection in the surface; this
is called a “proof roll.” At issue was
why this compaction test failed the first time.
Crispell-Snyder believed it was necessary to apply “fly ash” to solve
what it perceived to be a problem. The
Beckers thought the problem was the constant road traffic making the clay
subsurface pliable, which would resolve itself once all the construction
traffic was out of the way. The Beckers
wanted to wait until that occurred and see if the clay would stiffen. The Beckers’ expert explained to the jury
that the way to resolve a failed proof roll was precisely to simply let the
roadway dry out and keep traffic off it.
But Crispell-Snyder went ahead and applied the fly ash. The jury heard that traffic did wane for a
week after the fly ash was applied and the second proof roll passed but not,
according to the Becker’s expert, because of the fly ash. Thus, there was evidence that the change
order was unnecessary.
¶24 The
second change order concerned the rerouting of a sanitary sewer and force main
stemming from delayed construction. This
work had to be done before the road could be paved. The evidence was that there was a window of
opportunity to perform this work before the paving took place. The design was in place and approved, the
contractor was ready to go and, yet, it did not get done. The road was paved without the pipe. After paving, Crispell-Snyder knew that there
was an obstruction because someone placed extra concrete near the manhole in
the middle of the road. This obstruction
meant they could not drill to install the sewer. The jury had all the evidence it needed to
find that this “unforeseen condition” resulted from Crispell-Snyder’s own
decision not to go ahead with the sewer and pipe main before the road was
paved.
¶25 The
third change order had to do with as-built accounting charges that were
basically unprovable. The jury awarded
damages in the amount of the gravel quantities charged for fixing soft spots in
the roadway. There was inconsistent
testimony between the amount the contractor said he used and the amount
charged. The evidence was sufficient to
assess this overcharge to Crispell-Snyder.
¶26 Even
in the face of this evidence, Crispell-Snyder asserts that the Beckers waived
their right to dispute the change orders because they signed them.[2] But this is a question of fact, not a
question of law, and the jury obviously believed the Beckers’ claims that they
had no choice but to sign the change orders.
We will not disturb the jury’s verdict regarding the change orders.
B.
The Over-Inspection Fees
¶27 Evidence
also supports the jury’s finding that Crispell-Snyder billed the Beckers for
its over-inspection. On
cross-examination, one of Crispell-Snyder’s witnesses admitted that no
government regulation required the “24/7” inspection for which it billed the
Beckers. One of Crispell-Snyder’s own
employees testified that he logged inspection hours where he admitted that he
was there for no purpose. The Beckers’
expert testified that these and other charges were unnecessary and
unreasonable. Given this evidence, the
jury had sufficient, credible evidence to find that Crispell-Snyder breached
its contract by charging for its over-inspection and award the Beckers $12,000.
C.
The Excavator’s Lawsuit
¶28 Crispell-Snyder
also refutes the sufficiency of the evidence supporting the jury’s verdict on
the excavator’s claim.[3] At trial, the Beckers prevailed on their
argument that the only reason the excavator had a claim was because
Crispell-Snyder negligently provided exact quantities in its specifications,
known in the record as the “manual.”
¶29 Both
parties’ experts testified that the excavator was misled by the specific
quantities that Crispell-Snyder put in the manual. As a result, the excavator had to move more
dirt than it had originally thought.
Crispell-Snyder asserts that the Beckers’ expert’s testimony was based
on pure speculation. However, the trial
testimony shows that the excavator did use the quantity listed in the manual as
its benchmark. The Beckers’ expert also
explained why putting specific quantities in the manual is a negligent
act. Therefore, the jury had sufficient
evidence to find that Crispell-Snyder’s negligence caused the excavator’s
litigation.
COMMON-LAW
IMMUNITY
¶30 Crispell-Snyder
next cites law to argue that a road construction engineer is placed in a
position somewhat analogous to that of an umpire or an arbitrator. It is within the engineer’s professional
judgment as to what decisions to make regarding the amount of materials, the
need for delay, the decision to proceed and other decisions of that
nature. Crispell-Snyder cites
¶31 This
exhortation of the law is all fine, well and good, except for one thing. It never raised immunity as an affirmative
defense. Wisconsin Stat. § 802.06(2) (2005-06) states, in
pertinent part, that: “[e]very defense,
in law … except … improper venue … shall be
asserted in the responsive pleading .…”
(Emphasis added.) While the
statute provides exceptions, immunity is not one of them. The circuit court rejected the immunity
argument on this ground. Courts deem as
waived affirmative defenses not raised in accordance with § 802.06(2) in
responsive pleadings. See Gustavson v. O’Brien, 87
By
the Court.—Judgment
affirmed.
[1] The town was supposed to split Crispell-Snyder’s invoices 50/50 between the Beckers and a neighboring developer. However, the town ended up splitting the invoices 74/26 with the Beckers paying 74% and the neighboring developer paying 26%. The Beckers have not pursued this issue through an appeal.
[2] Crispell-Snyder
also relies on Milas v. Labor Ass’n of Wisconsin, Inc., 214
[3] Crispell-Snyder also asserts that the trial court should not have presented the excavator’s claim to the jury because it stems from an ancillary lawsuit. Crispell-Snyder cited no law supporting this assertion and the circumstances do not support it. The town settled the excavator’s lawsuit, and then sent the bill to the Beckers. And the claim involves the same parties and much of the same factual background. Therefore, the trial court properly submitted it to the jury.
[4] Crispell-Snyder also argues that even if the Beckers are third-party beneficiaries, public policy considerations must limit its liability as a matter of law. It posits that its professional judgment will be set aside and the town’s interest in properly built infrastructure will suffer if engineers are liable to private developers and have to satisfy the developer’s cost-saving objectives.
We agree with the circuit court, though, that the liability imposed on Crispell-Snyder is not so extraordinary or out of balance with the culpability of Crispell-Snyder, since the award is in fact-based on its own invoices. We also note that much of the reasoning in Crispell-Snyder’s public policy argument is similar to its common-law immunity argument, which we reject. Therefore, we refuse to bar liability as a matter of public policy under this case’s facts.
[5] Therefore,
we will not discuss Crispell-Snyder’s discretionary immunity claim as it
applies to the facts in this case. We do
note, however, that one of the exceptions to discretionary immunity listed in City
of Wauwatosa v. Jacobus & Winding Concrete Const. Co., 223