COURT OF APPEALS DECISION DATED AND FILED January 29, 2008 David R. Schanker Clerk of Court of Appeals |
|
NOTICE |
|
|
This opinion is subject to further editing. If published, the official version will appear in the bound volume of the Official Reports. A party may file with the Supreme Court a petition to review an adverse decision by the Court of Appeals. See Wis. Stat. § 808.10 and Rule 809.62. |
|
APPEAL
from orders of the circuit court for
Before Wedemeyer, Fine and Kessler, JJ.
¶1 KESSLER, J. The plaintiffs’ claims in this action arose from a defect in the construction of the roofs on the homes the plaintiffs occupy. Construction of the various homes was completed, at the latest, by August 1997. The defect was discovered in October 2005. This action was commenced in April 2006. The plaintiffs’ claims involve breach of contract, negligence, and misrepresentation. The trial court ruled that: (1) the contract claims were barred because the action was commenced after the applicable statute of limitations had expired, and because the contract in question was fundamentally for a product (a home) rather than for professional services; and (2) the negligence and misrepresentation claims were barred by the economic loss doctrine. The trial court then granted summary judgment to defendants dismissing all of the plaintiffs’ claims. We affirm.
BACKGROUND
¶2 Country Creek Homes, Inc. contracted with the original owners
to construct homes within the community of
¶3 In October 2005, a home inspector hired by one of the owners discovered that the felt paper, required to be placed under the shingles, had not been installed around the edges and peaks of the home’s roof. This caused water to penetrate and the roof to rot to such a degree that the inspector’s foot went through the roof. Subsequently, it was discovered that each residence occupied by one of the fifty-two plaintiffs in this case has the same roof defect.
¶4 Plaintiffs sued the general contractor Country Creek and its insurers, as well as the roofing subcontractors, Konecky and another with whom settlement was reached, and their insurers. Plaintiffs alleged breach of the express warranty in the construction contract, breach of contract by Country Creek, negligence in construction of the homes, negligent supervision of subcontractors by Country Creek, negligent or strict responsibility misrepresentation by Country Creek, and fraudulent misrepresentations by Country Creek in violation of Wis. Stat. § 100.18 (1995-96).[1]
¶5 Country Creek and Konecky moved for summary judgment arguing, as summarized by the trial court, that the contract-based claims are barred by a six-year statute of limitations, that the tort-based claims are barred by the economic loss doctrine, and that the fraudulent misrepresentation claims under Wis. Stat. § 100.18 (1995-96) are barred by a three-year statute of repose. Plaintiffs argued that Wis. Stat. § 893.89(3)(b) permitted this action for damages caused by a defect in the improvement of real estate, and that equitable estoppel should preclude application of the six-year statute of limitations in Wis. Stat. § 893.43 because Country Creek’s failure to disclose the defect was inequitable conduct.
¶6 The trial court found there was no dispute that:
· “All the homes at issue were … delivered to the … original homeowners, by August 1st of 1997.”
· “[T]he defect in the incomplete felt papering of the roofs of these … homes was in existence for approximately nine to ten years.”
· “[S]uit was commenced … April 7th of 2006.”
Based on those findings, the trial court concluded that the actions based on contract (i.e., breach of contract for failing to supervise the roofing subcontractor, and breach of warranty) were barred by the statute of limitations, Wis. Stat. § 893.43,[2] and dismissed the contract claims.
¶7 The contracts between the original-owner plaintiffs and Country Creek are part of this record. No party has argued here that other original owners had significantly different contracts with Country Creek. The contracts are all four-page documents (some with an additional page detailing extra construction changes and charges). All are on forms of the Metropolitan Builders Association of Greater Milwaukee; all are titled “Building Construction Agreement”; and all are alike except as to buyers, dates, specific price, and details of construction options selected by the buyer. The first page is devoted to identifying the parties, the total cost, specific construction allowances, and specific construction-related items included in the contract. The second page is devoted to financial matters such as down payment, financing contingencies, and buyer’s responsibility for insurance. The third page topics, some of which are deleted by cross outs, include: buyer establishing ownership of the lot (deleted); lien notice process; when construction will begin and end—and that builder will complete the building “in a good workmanlike manner in quality equal to the standards of the industry”—with exceptions as to completion date based on other circumstances; building site and weather conditions provisions (deleted); builder’s obligation to supervise the work; buyer’s responsibility to apply for utilities; provisions for work stoppage and payment defaults; possession and occupancy requirements; a warranty clause (substantially deleted); and a provision requiring arbitration of disputes under the contract. The fourth page actually fills approximately two-thirds of the page. It contains a paragraph entitled “air quality” (which appears to allocate to the buyer on occupancy any risk of poor air quality because of excessive moisture in the home), a provision discussing conditions relating to settlement of discrepancies involving the plans and specifications and noting builder’s obligation to comply with all soil erosion requirements, provisions regarding enforceability and finality of the agreement, and the earnest money receipt, and the signatures of all parties.
¶8 The trial court concluded that these contracts were ultimately for the purchase of a product—a home—at a fixed price. On that basis, the trial court concluded that the economic loss doctrine barred the tort claims and dismissed all of those claims. Plaintiffs appealed.
STANDARD OF REVIEW
¶9 We review the granting or denial of motions for summary
judgment de novo, applying the same
methodology and standards as the trial court. Green Spring Farms v. Kersten, 136
ANALYSIS
I. Contract claims
¶10 Plaintiffs, recognizing the six-year bar imposed by Wis. Stat. § 893.43, argue that, for policy reasons, we should apply the discovery rule applicable to tort claims[3] to contracts for construction of residences. Country Creek and Konecky argue that under settled Wisconsin law, claims brought for breach of contract six years after the breach occurred are barred, based on § 893.43, regardless of whether the party claiming damages from the breach had discovered the breach by that time.
¶11 For a century, our supreme court has held that a breach of
contract claim accrues at the time of the breach, even if the defect is latent
and even if the party may not have known of its existence. See
CLL
Assocs. Ltd. P’ship v. Arrowhead Pac. Corp., 174 Wis. 2d 604, 609, 497
N.W.2d 115 (1993); State v. Holland Plastics Co., 111 Wis. 2d 497, 506, 331 N.W.2d
320 (1983); Denzer v. Rouse, 48 Wis. 2d 528, 531, 180 N.W.2d 521 (1970) overruled on other grounds by Hansen
v. A.H. Robins, Inc., 113
¶12 The policy basis for the breach of contract rule was explained
at length in CLL Assocs. Ltd., where the supreme court was specifically
asked, as plaintiffs ask here, to apply the discovery rule in contract actions.
Our holding rests on the fact that policy considerations do not favor a broadly applied discovery rule in the contract context. If the general rule that we uphold today creates unjust results in specific situations not now before this court, i.e. in the consumer context where contracting consumers have limited bargaining power, the legislature, with its greater resources for weighing policy, is best equipped to enact specific ameliorative laws
¶13 We cannot modify or overrule supreme court holdings. Cook v. Cook, 208
II. Negligence
claims
¶14 A tort cause of action “accrues” when the injury is discovered,
or reasonably should have been discovered. Hansen, 113
¶15 A common law tort claim, based on negligent performance of professional services, exists independently of a contract whose primary purpose is to obtain those professional services and the contract merely triggers the duty. See Milwaukee Partners, 169 Wis. 2d at 361-62 (holding that, in a contract with engineers to determine structural soundness of a building, the “[f]ailure to exercise ordinary care in fulfillment of [a] contract is tort if common-law duty to exercise ordinary care exists independent of the contract and [the] ‘contract is mere[ly the] inducement creating the state of things which furnishes the occasion of the tort’” (citation and one set of internal quotations omitted)); see also Kerry Inc., 280 Wis. 2d 418, ¶9 (holding that in contract with architects to determine structural stability of renovation site, “claims against architects for improperly performed work may often sound in either contract or tort, but their common-law duty to exercise the standard of professional care for architects exists independent of any contract, which merely ‘furnishe[s] the occasion’ for fulfillment of that duty”) (citations and one set of internal quotations omitted)).
¶16 However, if the contract is predominantly one for a product, although services are required to obtain the product, the tort claim is barred by the economic loss doctrine.[5] Linden, 283 Wis. 2d 606, ¶8 (“We use the predominant purpose test to determine whether a mixed contract for products and services is predominantly a sale of a product and therefore subject to the economic loss doctrine, or predominantly a contract for services and therefore not subject to the economic loss doctrine.” (internal citations omitted)); see also 1325 North Van Buren, LLC v. T-3 Group, Ltd., 2006 WI 94, ¶5, 293 Wis. 2d 410, 716 N.W.2d 822 (holding that the economic loss doctrine applies to contracts for services and products where the predominant purpose of the contract is to construct a condominium complex and adjacent parking garages).
¶17 It is undisputed that the contracts here for the construction
of homes were titled “Building Construction Agreement,” and were printed on a
form identified as coming from the Metropolitan Builders Association of Greater
Milwaukee. We have described in detail the
terms of the contract. The references to
Country Creek’s obligations cover a very small part of the contract as a whole. The references primarily relate to producing
a house within a particular time and in accord with detailed plans and
specifications (which are not part of the record). We conclude, based on the terms of the
contract taken as a whole, that the predominant purpose here was to produce a
product—a residence—for a fixed price. Thus,
under the teachings of
CONCLUSION
¶18 Consistent with the holdings in CLL Assocs. Ltd. that Wis. Stat. § 893.43, the six-year
statute of limitations applicable to contract actions, requires commencement of
a suit within six years from the date the contract is breached, not within six
years from the date the breach is discovered, plaintiffs’ contract claims are
time-barred. Because the contracts here
were predominantly for the purchase of a product, consistent with the holdings
of
By the Court.—Orders affirmed.
Not recommended for publication in the official reports.
[1] All references to the Wisconsin Statutes are to the 2005-06 version unless otherwise noted. Additionally, none of the statutes cited in this opinion have changed substantively from the 1995-96 version to the present, except for Wis. Stat. § 100.18, which was modified in 1997 (motor fuel provision); 2001 (use of area name by out-of-area businesses); and 2003 (liquidation sales).
[2] Wisconsin Stat. § 893.43, entitled, “Action on contract,” provides: “An action upon any contract, obligation or liability, express or implied, including an action to recover fees for professional services, except those mentioned in s. 893.40, shall be commenced within 6 years after the cause of action accrues or be barred.”
[3] The
statute of limitations for tort claims begins to run when the injured party
learned, discovered or with reasonable diligence should have learned of the
conduct causing the injury. Hansen
v. A.H. Robins, Inc., 113
[4] Wisconsin Stat. § 893.53 provides that “[a]n action to recover damages for an injury to the ... rights of another, not arising on contract, shall be commenced within 6 years after the cause of action accrues, except where a different period is expressly prescribed, or be barred.”
[5] “‘The economic loss doctrine is a judicially created doctrine under which a purchaser of a product cannot recover from a manufacturer on a tort theory for damages that are solely economic.’” 1325 North Van Buren, LLC v. T-3 Group, Ltd., 2006 WI 94, ¶24, 293 Wis. 2d 410, 716 N.W.2d 822 (citation and one set of internal quotations omitted). There is no claim in this record of any loss other than repair and/or replacement of the roofs.
[6] Plaintiffs
did not argue on appeal that the trial court erred in dismissing the various
misrepresentation claims. Issues not
raised on appeal are deemed abandoned. Adler
v. D & H Indus., Inc., 2005 WI App 43, ¶18, 279